Assessment Year | 2005 |
---|---|
Principal Product | Laminated Shingles |
NAICS | 324122: Asphalt Shingle and Coating Materials Manufacturing |
SIC | 2952: Asphalt Felts and Coatings |
Sales Range | $50 M to 100M |
# of Employees | 112 |
Plant Area |
150,000
ft2
|
Annual Production | 2,360,000
pieces
|
Production Hrs. Annual | 8,424
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $310,932 | 8,601,615 |
kWh
|
$0.036 |
Electricity Demand | $36,050 | 13,364 |
kW-mo/yr
|
$2.70 |
Electricity Fees | $28,540 | - |
|
- |
Natural Gas | $375,327 | 54,970 |
MMBtu
|
$6.83 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $92,581 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $59,490 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,764 | $944 |
$1,669
40,500
kWh
|
$95
-
kW-mo/yr
|
- | - | |
02 | 2.1133: Adjust burners for efficient operation | $11,058 | $1,000 | - | - |
$11,058
-
MMBtu
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $16,504 | $7,500 |
$15,618
379,080
kWh
|
$886
-
kW-mo/yr
|
- | - | |
04 | 2.1133: Adjust burners for efficient operation | $26,869 | $3,000 | - | - |
$26,869
-
MMBtu
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,965 | $13,380 |
$4,699
114,061
kWh
|
$266
-
kW-mo/yr
|
- | - | |
06 | 2.7111: Reduce illumination to minimum necessary levels | $10,157 | $27,000 |
$9,612
233,300
kWh
|
$545
-
kW-mo/yr
|
- | - | |
07 | 2.7134: Use photocell controls | $2,516 | $570 |
$2,516
61,080
kWh
|
- | - | - | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $779 | $695 |
$733
17,795
kWh
|
$46
-
kW-mo/yr
|
- | - | |
09 | 2.3212: Optimize plant power factor | $17,969 | $6,055 | - | - | - | $17,969 | |
TOTAL RECOMMENDED | $92,581 | $60,144 |
$34,847
845,816
kWh
|
$1,838
-
kW-mo/yr
|
$37,927
-
MMBtu
|
$17,969 | ||
TOTAL IMPLEMENTED | $59,490 | $13,709 |
$20,536
498,455
kWh
|
$1,027
-
kW-mo/yr
|
$37,927
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs