Assessment Year | 2005 |
---|---|
Principal Product | Hard and Soft Candy |
NAICS | 311340: Nonchocolate Confectionery Manufacturing |
SIC | 2064: Candy and Other Confectionery Products |
Sales Range | $100 M to 500M |
# of Employees | 276 |
Plant Area |
146,800
ft2
|
Annual Production | 32,000,000
lb
|
Production Hrs. Annual | 5,880
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $601,678 | 17,357,760 |
kWh
|
$0.035 |
Electricity Demand | $414,881 | 35,814 |
kW-mo/yr
|
$11.58 |
Electricity Fees | $18,606 | - |
|
- |
Natural Gas | $1,097,083 | 258,522 |
MMBtu
|
$4.24 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $269,648 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $250,217 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2622: Replace existing chiller with high efficiency model | $241,590 | $283,800 |
$45,570
1,470,000
kWh
|
$30,750
-
kW-mo/yr
|
- | $185,000 |
$(-19,730.0)
-
Tgal
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,617 | $22,400 |
$3,731
120,344
kWh
|
$2,886
-
kW-mo/yr
|
- | - | - | |
03 | 2.1231: Establish burner maintenance schedule for boilers | $2,775 | $900 | - | - |
$2,775
-
MMBtu
|
- | - | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $14,900 | $25,600 | - | - |
$14,900
-
MMBtu
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,756 | $1,785 |
$1,741
14,717
kWh
|
$15
-
kW-mo/yr
|
- | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,010 | $850 |
$1,200
38,714
kWh
|
$810
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $269,648 | $335,335 |
$52,242
1,643,775
kWh
|
$34,461
-
kW-mo/yr
|
$17,675
-
MMBtu
|
$185,000 |
$(-19,730.0)
-
Tgal
|
||
TOTAL IMPLEMENTED | $250,217 | $307,050 |
$50,501
1,629,058
kWh
|
$34,446
-
kW-mo/yr
|
- | $185,000 |
$(-19,730.0)
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs