ITAC Assessment: GT0800
ITAC logo
ITAC Assessment: GT0800
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Hard and Soft Candy
NAICS 311340: Nonchocolate Confectionery Manufacturing
SIC 2064: Candy and Other Confectionery Products
Sales Range $100
M
to 500
M
# of Employees 276
Plant Area 146,800
ft2
Annual Production 32,000,000
lb
Production Hrs. Annual 5,880
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $601,678 17,357,760
kWh
Electricity Demand $414,881 35,814
kW-mo/yr
Electricity Fees $18,606 -
Natural Gas $1,097,083 258,522
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $269,648 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $250,217

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Water Consumption Savings
01 2.2622: Replace existing chiller with high efficiency model $241,590 $283,800 $45,570
1,470,000
kWh
$30,750
-
kW-mo/yr
- $185,000 $(-19,730.0)
-
Tgal
02 2.7142: Utilize higher efficiency lamps and/or ballasts $6,617 $22,400 $3,731
120,344
kWh
$2,886
-
kW-mo/yr
- - -
03 2.1231: Establish burner maintenance schedule for boilers $2,775 $900 - - $2,775
-
MMBtu
- -
04 2.2414: Use waste heat from hot flue gases to preheat $14,900 $25,600 - - $14,900
-
MMBtu
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,756 $1,785 $1,741
14,717
kWh
$15
-
kW-mo/yr
- - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,010 $850 $1,200
38,714
kWh
$810
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $269,648 $335,335 $52,242
1,643,775
kWh
$34,461
-
kW-mo/yr
$17,675
-
MMBtu
$185,000 $(-19,730.0)
-
Tgal
TOTAL IMPLEMENTED $250,217 $307,050 $50,501
1,629,058
kWh
$34,446
-
kW-mo/yr
- $185,000 $(-19,730.0)
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs