ITAC Assessment: GT0779
ITAC logo
ITAC Assessment: GT0779
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product BOTTLES
NAICS 323111: Commercial Printing (except Screen and Books)
SIC 2759: Commercial Printing, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 60
Plant Area 60,000
ft2
Annual Production 35,000,000
pieces
Production Hrs. Annual 4,160
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $93,401 2,989,166
kWh
Natural Gas $10,988 967
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,696 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,403

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.1321: Replace fossil fuel equipment with electrical equipment $1,183 $5,000 - - $1,183
-
MMBtu
02 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas $590 $2,700 $590
21,752
kWh
- -
03 2.2437: Recover waste heat from equipment $2,642 $5,350 $(-33.0)
(-1,222)
kWh
- $2,675
-
MMBtu
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $327 $300 $327
12,125
kWh
- -
05 2.4324: Replace hydraulic / pneumatic equipment with electric equipment $2,090 $4,600 $2,090
77,300
kWh
- -
06 2.7111: Reduce illumination to minimum necessary levels $1,561 $320 $681
25,196
kWh
$880
-
kW-mo/yr
-
07 2.7135: Install occupancy sensors $303 $1,000 $303
11,225
kWh
- -
TOTAL RECOMMENDED $8,696 $19,270 $3,958
146,376
kWh
$880
-
kW-mo/yr
$3,858
-
MMBtu
TOTAL IMPLEMENTED $2,403 $9,000 $1,220
45,102
kWh
- $1,183
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs