| Assessment Year | 2003 |
|---|---|
| Principal Product | LAWNMOWER BLADES |
| NAICS | 333112: Lawn and Garden Tractor and Home Lawn and Garden Equipment Manufacturing |
| SIC | 3524: Lawn and Garden Tractors and Home Lawn and Garden Equipment |
| Sales Range | $5 M to 10M |
| # of Employees | 125 |
| Plant Area |
90,000
ft2
|
| Annual Production | 8,000,000
pieces
|
| Production Hrs. Annual | 3,000
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $235,756 | 8,515,332 |
kWh
|
$0.028 |
| Electricity Demand | $213,061 | 18,291 |
kW-mo/yr
|
$11.65 |
| Natural Gas | $93,844 | 14,063 |
MMBtu
|
$6.67 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $51,193 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $25,088 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2514: Cover open tanks | $17,200 | - |
$13,050
680,400
kWh
|
$4,150
-
kW-mo/yr
|
- | |
| 02 | 2.4314: Use synthetic lubricant | $1,055 | - |
$400
13,700
kWh
|
$655
-
kW-mo/yr
|
- | |
| 03 | 2.2514: Cover open tanks | $7,550 | $2,505 |
$1,190
40,470
kWh
|
$660
-
kW-mo/yr
|
$5,700
-
MMBtu
|
|
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $620 | $1,555 |
$270
9,137
kWh
|
$350
-
kW-mo/yr
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,750 | $710 |
$3,750
127,400
kWh
|
- | - | |
| 06 | 2.1221: Replace obsolete burners with more efficient ones | $17,500 | $38,000 |
$8,225
279,500
kWh
|
$4,425
-
kW-mo/yr
|
$4,850
-
MMBtu
|
|
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,150 | $5,635 |
$200
6,670
kWh
|
$950
-
kW-mo/yr
|
- | |
| 08 | 2.4133: Use most efficient type of electric motors | $2,368 | $36,246 |
$850
28,896
kWh
|
$1,518
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $51,193 | $84,651 |
$27,935
1,186,173
kWh
|
$12,708
-
kW-mo/yr
|
$10,550
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $25,088 | $44,146 |
$18,120
852,503
kWh
|
$6,968
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs