ITAC Assessment: GT0756
ITAC logo
ITAC Assessment: GT0756
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product SLURRY PUMPS; IRON CASTINGS
NAICS 331511: Iron Foundries
SIC 3325: Steel Foundries, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 190
Plant Area 215,000
ft2
Annual Production 6,250
ton
Production Hrs. Annual 8,400
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $558,177 16,526,346
kWh
Electricity Demand $250,749 71,161
kW-mo/yr
Electricity Fees $9,778 -
Fuel Oil #2 $7,021 1,177
MMBtu
Other Gas $45,016 4,981
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $219,457 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Fuel Oil #2 Savings Other Energy Savings Water Disposal Savings Water Consumption Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $510 $1,100 n/a $510
14,443
kWh
- - - - - - -
02 2.2514: Cover open tanks $18,300 $3,000 n/a $18,300
515,200
kWh
- - - - - - -
03 2.2223: Enhance sensitivity of temperature control and cutoff $22,800 $5,610 n/a - - - $22,800
-
MMBtu
- - - -
04 2.1121: Use insulation in furnaces to facilitate heating / cooling $2,950 $1,620 n/a - - - $2,950
-
MMBtu
- - - -
05 3.4111: Use closed cycle process to minimize waste water production $10,000 $35,955 n/a - - - - - - - $10,000
-
Tgal
06 3.4116: Meter recycled water (to reduce sewer charges) $2,680 $1,850 n/a - - - - - - $2,680
-
Tgal
-
07 2.7291: Reschedule and rearrange multiple-source heating systems $56,040 $1,500 n/a - - - $56,040
-
MMBtu
- - - -
08 2.4134: Replace electric motor with fossil fuel engine $89,400 $200,000 n/a $54,830
895,860
kWh
$76,543
-
kW-mo/yr
$5,847 - $(-47,820.0)
-
MMBtu
- - -
09 2.7124: Make a practice of turning off lights when not needed $784 - n/a $784
22,080
kWh
- - - - - - -
10 2.7121: Utilize daylight whenever possible in lieu of artificial light $5,098 $10,980 n/a $5,098
143,520
kWh
- - - - - - -
11 2.8114: Change rate schedules or other changes in utility service $3,820 - n/a - - $3,820 - - - - -
12 2.2511: Insulate bare equipment $1,474 $1,730 n/a - - - - - $1,474
-
MMBtu
- -
13 2.6218: Turn off equipment when not in use $556 - n/a $556
15,700
kWh
- - - - - - -
14 2.8112: Combine utility meters $2,980 - n/a - - $2,980 - - - - -
15 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,065 - n/a $2,065
57,800
kWh
- - - - - - -
TOTAL RECOMMENDED $219,457 $263,345 $82,143
1,664,603
kWh
$76,543
-
kW-mo/yr
$12,647 $81,790
-
MMBtu
$(-47,820.0)
-
MMBtu
$1,474
-
MMBtu
$2,680
-
Tgal
$10,000
-
Tgal
TOTAL IMPLEMENTED - - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Fuel Oil #2 Savings Other Energy Savings Water Disposal Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs