| Assessment Year | 2003 |
|---|---|
| Principal Product | CARBONATED DRINKS |
| NAICS | 312111: Soft Drink Manufacturing |
| SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
| Sales Range | $100 M to 500M |
| # of Employees | 302 |
| Plant Area |
404,211
ft2
|
| Annual Production | 49,484
ton
|
| Production Hrs. Annual | 4,080
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $594,704 | 12,579,650 |
kWh
|
$0.047 |
| Natural Gas | $452,000 | 106,251 |
MMBtu
|
$4.25 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $80,661 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $15,743 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.1231: Establish burner maintenance schedule for boilers | $5,393 | $1,350 | - | - |
$5,393
-
MMBtu
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $226 | $400 |
$214
7,571
kWh
|
$12 | - | - | |
| 03 | 2.1111: Control pressure on steamer operations | $1,680 | - | - | - |
$1,680
-
MMBtu
|
- | |
| 04 | 2.4314: Use synthetic lubricant | $6,298 | - |
$5,942
210,700
kWh
|
$356 | - | - | |
| 05 | 2.2136: Install / repair insulation on steam lines | $1,058 | $372 | - | - |
$1,058
-
MMBtu
|
- | |
| 06 | 2.2121: Increase amount of condensate returned | $17,688 | $5,200 | - | - |
$17,200
-
MMBtu
|
$488
-
Tgal
|
|
| 07 | 2.4322: Use or replace with energy efficient substitutes | $35,980 | $15,000 | - | - |
$35,980
-
MMBtu
|
- | |
| 08 | 2.2621: Modify refrigeration system to operate at a lower pressure | $9,570 | $27,000 |
$9,570
301,090
kWh
|
- | - | - | |
| 09 | 2.4322: Use or replace with energy efficient substitutes | $2,768 | $14,000 |
$2,612
92,611
kWh
|
$156 | - | - | |
| TOTAL RECOMMENDED | $80,661 | $63,322 |
$18,338
611,972
kWh
|
$524 |
$61,311
-
MMBtu
|
$488
-
Tgal
|
||
| TOTAL IMPLEMENTED | $15,743 | $16,122 |
$8,768
310,882
kWh
|
$524 |
$6,451
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs