Assessment Year | 2002 |
---|---|
Principal Product | Kaolin |
NAICS |
n/a
|
SIC | 3295: Minerals and Earths, Ground or Otherwise Treated |
Sales Range | $10 M to 50M |
# of Employees | 460 |
Plant Area |
145,000
ft2
|
Annual Production | 2,200,000,000
lb
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,309,623 | 56,955,634 |
kWh
|
$0.041 |
Natural Gas | $3,663,100 | 1,046,000 |
MMBtu
|
$3.50 |
Fuel Oil #2 | $3,327 | 679 |
MMBtu
|
$4.90 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,309,514 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $114,954 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Water Consumption Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $80,749 | - | - | $80,749 | - | - | - | - | - | |
02 | 2.7124: Make a practice of turning off lights when not needed | $204 | - |
$204
5,392
kWh
|
- | - | - | - | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $3,490 | $2,100 |
$3,490
91,652
kWh
|
- | - | - | - | - | - | |
04 | 2.4314: Use synthetic lubricant | $9,470 | - |
$9,470
250,200
kWh
|
- | - | - | - | - | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $16,970 | $15,430 |
$16,970
448,331
kWh
|
- | - | - | - | - | - | |
06 | 2.1133: Adjust burners for efficient operation | $268,450 | $200,000 | - | - |
$268,450
-
MMBtu
|
- | - | - | - | |
07 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $674,846 | $2,070,000 |
$1,459,000
38,556,000
kWh
|
- |
$(-591,374.0)
-
MMBtu
|
- | $(-192,780.0) | - | - | |
08 | 2.4133: Use most efficient type of electric motors | $13,635 | $98,936 |
$13,635
360,200
kWh
|
- | - | - | - | - | - | |
09 | 3.4154: Eliminate leaks in water lines and valves | $14,600 | - | - | - | - | - | - |
$14,600
-
Tgal
|
- | |
10 | 3.5217: Reuse / recycle/ sell paper products | $3,600 | $6,700 | - | - | - |
$3,600
-
lb
|
- | - | - | |
11 | 4.611: Begin a practice of predictive / preventative maintenance | $223,500 | $100,000 | - | - | - | - | - | - | $223,500 | |
TOTAL RECOMMENDED | $1,309,514 | $2,493,166 |
$1,502,769
39,711,775
kWh
|
$80,749 |
$(-322,924.0)
-
MMBtu
|
$3,600
-
lb
|
$(-192,780.0) |
$14,600
-
Tgal
|
$223,500 | ||
TOTAL IMPLEMENTED | $114,954 | $121,066 |
$30,605
808,531
kWh
|
$80,749 | - |
$3,600
-
lb
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Water Consumption Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs