Assessment Year | 2002 |
---|---|
Principal Product | corrugated cardboard |
NAICS |
n/a
|
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $10 M to 50M |
# of Employees | 143 |
Plant Area |
200,000
ft2
|
Annual Production | 804,000
thousand feet
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $120,269 | 4,262,603 |
kWh
|
$0.028 |
Electricity Demand | $144,890 | 9,088 |
kW-mo/yr
|
$15.94 |
Natural Gas | $221,241 | 44,037 |
MMBtu
|
$5.02 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $41,100 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $41,100 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,194 | $6,268 |
$715
26,084
kWh
|
$1,479
-
kW-mo/yr
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,887 | $4,500 |
$974
3,517
kWh
|
$913
-
kW-mo/yr
|
- | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $17,145 | $2,556 |
$8,857
327,081
kWh
|
$8,288
-
kW-mo/yr
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,400 | $2,250 |
$1,757
64,771
kWh
|
$1,643
-
kW-mo/yr
|
- | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $6,705 | - | - | - |
$6,705
-
MMBtu
|
|
06 | 2.4133: Use most efficient type of electric motors | $9,769 | $31,236 |
$4,457
164,420
kWh
|
$5,312
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $41,100 | $46,810 |
$16,760
585,873
kWh
|
$17,635
-
kW-mo/yr
|
$6,705
-
MMBtu
|
||
TOTAL IMPLEMENTED | $41,100 | $46,810 |
$16,760
585,873
kWh
|
$17,635
-
kW-mo/yr
|
$6,705
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs