| Assessment Year | 2002 |
|---|---|
| Principal Product | mattresses, box springs |
| NAICS |
n/a
|
| SIC | 2515: Mattresses, Foundations, and Convertible Beds |
| Sales Range | $100 M to 500M |
| # of Employees | 132 |
| Plant Area |
200,000
ft2
|
| Annual Production | 325,000
pieces
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | South Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $72,396 | 1,181,419 |
kWh
|
$0.061 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $4,951 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,058 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7243: Improve air circulation with destratification fans / other methods | $2,238 | $5,018 | - | - | $2,238 | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $193 | $330 | - | - | $193 | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $170 | - | - | - | - |
$170
-
MMBtu
|
|
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $715 | $2,240 |
$330
2,394,490
kWh
|
$280
-
kW-mo/yr
|
$105 | - | |
| 05 | 3.1161: Eliminate/reduce an operation | $530 | $675 |
$230
1,668,230
kWh
|
$246
-
kW-mo/yr
|
$54 | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,105 | $4,013 |
$401
2,908,265
kWh
|
$627
-
kW-mo/yr
|
$77 | - | |
| TOTAL RECOMMENDED | $4,951 | $12,276 |
$961
6,970,985
kWh
|
$1,153
-
kW-mo/yr
|
$2,667 |
$170
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $4,058 | $11,271 |
$731
5,302,755
kWh
|
$907
-
kW-mo/yr
|
$2,420 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs