| Assessment Year | 2002 |
|---|---|
| Principal Product | Extruded Plastic |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 4 |
| Plant Area |
34,500
ft2
|
| Annual Production | 5,047,243
pieces
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $86,777 | 1,032,000 |
kWh
|
$0.084 |
| Natural Gas | $2,933 | 254 |
MMBtu
|
$11.55 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $23,481 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $18,360 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,492 | $750 |
$599
17,200
kWh
|
$1,856
-
kW-mo/yr
|
- | $37 | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,952 | $6,346 |
$698
20,079
kWh
|
$1,225
-
kW-mo/yr
|
- | $29 | - | |
| 03 | 3.7311: Maintain machines to reduce leaks | $2,765 | $3,150 | - | - |
$1,269
-
lb
|
- | $1,496 | |
| 04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $13,916 | - | - |
$13,710
-
kW-mo/yr
|
- | $206 | - | |
| 05 | 2.2511: Insulate bare equipment | $2,356 | $1,555 |
$1,417
35,644
kWh
|
$939
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $23,481 | $11,801 |
$2,714
72,923
kWh
|
$17,730
-
kW-mo/yr
|
$1,269
-
lb
|
$272 | $1,496 | ||
| TOTAL IMPLEMENTED | $18,360 | $7,096 |
$1,297
37,279
kWh
|
$16,791
-
kW-mo/yr
|
- | $272 | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs