Assessment Year | 2002 |
---|---|
Principal Product | Secondary Paperboard Packages |
NAICS |
n/a
|
SIC | 2657: Folding Paperboard Boxes, Including Sanitary |
Sales Range | $100 M to 500M |
# of Employees | 225 |
Plant Area |
1,000,000
ft2
|
Annual Production | 1,175,000
pieces
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $908,386 | 18,405,154 |
kWh
|
$0.049 |
Electricity Fees | $63,587 | - |
|
- |
Natural Gas | $692,877 | 107,994 |
MMBtu
|
$6.42 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $629,081 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $55,863 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | LPG Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $43,102 | $10,500 |
$2,827
81,000
kWh
|
- |
$(-1,725.0)
-
MMBtu
|
- | $2,000 | - | $40,000 | |
02 | 4.444: Install system to collect scrap | $540,000 | $192,000 | - | - | - | - | $540,000 | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,758 | - |
$3,509
101,262
kWh
|
$249 | - | - | - | - | - | |
04 | 2.7144: Install spectral reflectors / delamp | $2,446 | $2,550 |
$2,286
65,324
kWh
|
$160 | - | - | - | - | - | |
05 | 2.2437: Recover waste heat from equipment | $10,185 | $35,000 | - | - |
$10,185
-
MMBtu
|
- | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,301 | $10,007 |
$4,019
114,839
kWh
|
$282 | - | - | - | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,114 | $400 |
$1,434
40,960
kWh
|
$2,680 | - | - | - | - | - | |
08 | 3.5111: Filter and reuse hydraulic oil | $1,900 | - | - | - | - | - | - | $(-600.0) | $2,500 | |
09 | 2.1332: Convert combustion equipment to burn natural gas | $19,275 | $45,000 | - | - |
$(-16,425.0)
-
MMBtu
|
$35,700
-
MMBtu
|
- | - | - | |
TOTAL RECOMMENDED | $629,081 | $295,457 |
$14,075
403,385
kWh
|
$3,371 |
$(-7,965.0)
-
MMBtu
|
$35,700
-
MMBtu
|
$542,000 | $(-600.0) | $42,500 | ||
TOTAL IMPLEMENTED | $55,863 | $23,457 |
$10,566
302,123
kWh
|
$3,122 |
$(-1,725.0)
-
MMBtu
|
- | $2,000 | $(-600.0) | $42,500 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | LPG Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs