ITAC Assessment: GT0720
ITAC logo
ITAC Assessment: GT0720
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Pork Meat Products
NAICS
n/a
SIC 2011: Meat Packing Plants
Sales Range $1
M
to 5
M
# of Employees 24
Plant Area 21,280
ft2
Annual Production 2,500,000
lb
Production Hrs. Annual 2,295
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $10,358 709,440
kWh
Electricity Demand $23,579 1,604
kW-mo/yr
Electricity Fees $8,208 -
Natural Gas $19,522 2,551
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $107,496 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,881

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Water Consumption Savings Primary Product Savings
01 2.1231: Establish burner maintenance schedule for boilers $337 $1,000 - - - $337
-
MMBtu
- - - -
02 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas $1,475 $600 $111
7,625
kWh
$1,279
-
kW-mo/yr
$85 - - - - -
03 2.2136: Install / repair insulation on steam lines $467 $943 - - - $467
-
MMBtu
- - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,472 $6,151 $227
15,547
kWh
$1,161
-
kW-mo/yr
$84 - - - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $277 $324 $43
2,974
kWh
$218
-
kW-mo/yr
$16 - - - - -
06 2.7232: Replace existing hvac unit with high efficiency model $658 $982 - - - $658
-
MMBtu
- - - -
07 2.1241: Reduce excessive boiler blowdown $1,320 $50 - - - $1,270
-
MMBtu
$30
-
Tgal
- $20
-
Tgal
-
08 3.5315: Lease / purchase baler; sell cardboard to recycler $7,740 - - - - - - $7,740
-
lb
- -
09 4.445: Install equipment to move product $93,750 $1,700 - - - - - - - $93,750
TOTAL RECOMMENDED $107,496 $11,750 $381
26,146
kWh
$2,658
-
kW-mo/yr
$185 $2,732
-
MMBtu
$30
-
Tgal
$7,740
-
lb
$20
-
Tgal
$93,750
TOTAL IMPLEMENTED $4,881 $8,125 $381
26,146
kWh
$2,658
-
kW-mo/yr
$185 $1,607
-
MMBtu
$30
-
Tgal
- $20
-
Tgal
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Water Consumption Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs