| Assessment Year | 2001 |
|---|---|
| Principal Product | Pork Meat Products |
| NAICS |
n/a
|
| SIC | 2011: Meat Packing Plants |
| Sales Range | $1 M to 5M |
| # of Employees | 24 |
| Plant Area |
21,280
ft2
|
| Annual Production | 2,500,000
lb
|
| Production Hrs. Annual | 2,295
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $10,358 | 709,440 |
kWh
|
$0.015 |
| Electricity Demand | $23,579 | 1,604 |
kW-mo/yr
|
$14.70 |
| Electricity Fees | $8,208 | - |
|
- |
| Natural Gas | $19,522 | 2,551 |
MMBtu
|
$7.65 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $107,496 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,881 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Water Consumption Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1231: Establish burner maintenance schedule for boilers | $337 | $1,000 | - | - | - |
$337
-
MMBtu
|
- | - | - | - | |
| 02 | 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas | $1,475 | $600 |
$111
7,625
kWh
|
$1,279
-
kW-mo/yr
|
$85 | - | - | - | - | - | |
| 03 | 2.2136: Install / repair insulation on steam lines | $467 | $943 | - | - | - |
$467
-
MMBtu
|
- | - | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,472 | $6,151 |
$227
15,547
kWh
|
$1,161
-
kW-mo/yr
|
$84 | - | - | - | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $277 | $324 |
$43
2,974
kWh
|
$218
-
kW-mo/yr
|
$16 | - | - | - | - | - | |
| 06 | 2.7232: Replace existing hvac unit with high efficiency model | $658 | $982 | - | - | - |
$658
-
MMBtu
|
- | - | - | - | |
| 07 | 2.1241: Reduce excessive boiler blowdown | $1,320 | $50 | - | - | - |
$1,270
-
MMBtu
|
$30
-
Tgal
|
- |
$20
-
Tgal
|
- | |
| 08 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $7,740 | - | - | - | - | - | - |
$7,740
-
lb
|
- | - | |
| 09 | 4.445: Install equipment to move product | $93,750 | $1,700 | - | - | - | - | - | - | - | $93,750 | |
| TOTAL RECOMMENDED | $107,496 | $11,750 |
$381
26,146
kWh
|
$2,658
-
kW-mo/yr
|
$185 |
$2,732
-
MMBtu
|
$30
-
Tgal
|
$7,740
-
lb
|
$20
-
Tgal
|
$93,750 | ||
| TOTAL IMPLEMENTED | $4,881 | $8,125 |
$381
26,146
kWh
|
$2,658
-
kW-mo/yr
|
$185 |
$1,607
-
MMBtu
|
$30
-
Tgal
|
- |
$20
-
Tgal
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Water Consumption Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs