| Assessment Year | 2001 |
|---|---|
| Principal Product | Circuit Boards |
| NAICS |
n/a
|
| SIC | 3672: Printed Circuit Boards |
| Sales Range | $10 M to 50M |
| # of Employees | 75 |
| Plant Area |
50,000
ft2
|
| Annual Production | 250,000
pieces
|
| Production Hrs. Annual | 5,000
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $18,749 | 604,800 |
kWh
|
$0.031 |
| Electricity Demand | $19,634 | 1,823 |
kW-mo/yr
|
$10.77 |
| Electricity Fees | $7,557 | - |
|
- |
| Natural Gas | $3,061 | 319 |
MMBtu
|
$9.60 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $10,436 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $860 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8114: Change rate schedules or other changes in utility service | $6,495 | $2,000 | - | - | $6,495 | - | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,025 | $3,725 |
$981
31,654
kWh
|
$910
-
kW-mo/yr
|
$134 | - | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $845 | $1,450 |
$277
8,936
kWh
|
$514
-
kW-mo/yr
|
$54 | - | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $331 | $310 |
$64
2,078
kWh
|
$30
-
kW-mo/yr
|
- | - | $27 | $210 | |
| 05 | 2.6241: Reduce temperature of process equipment when on standby | $15 | - |
$15
495
kWh
|
- | - | - | - | - | |
| 06 | 2.4314: Use synthetic lubricant | $75 | - |
$24
778
kWh
|
$46
-
kW-mo/yr
|
$5 | - | - | - | |
| 07 | 2.2222: Convert liquid heaters from underfiring to immersion or submersion heating | $140 | $800 |
$140
4,463
kWh
|
- | - | - | - | - | |
| 08 | 2.7224: Reduce space conditioning during non-working hours | $510 | $225 |
$60
1,940
kWh
|
- | - |
$450
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $10,436 | $8,510 |
$1,561
50,344
kWh
|
$1,500
-
kW-mo/yr
|
$6,688 |
$450
-
MMBtu
|
$27 | $210 | ||
| TOTAL IMPLEMENTED | $860 | $1,450 |
$292
9,431
kWh
|
$514
-
kW-mo/yr
|
$54 | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs