Assessment Year | 1999 |
---|---|
Principal Product | kitchen & bath cabinets |
NAICS |
n/a
|
SIC | 2434: Wood Kitchen Cabinets |
Sales Range | $5 M to 10M |
# of Employees | 100 |
Plant Area |
38,440
ft2
|
Annual Production | 32,000
pieces
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Wyoming |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $14,553 | 632,474 |
kWh
|
$0.023 |
Electricity Demand | $16,572 | 1,840 |
kW-mo/yr
|
$9.01 |
Electricity Fees | $300 | - |
|
- |
Natural Gas | $6,757 | 1,776 |
MMBtu
|
$3.80 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $115,040 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $83,490 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,160 | $5,000 | - |
$2,160
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,270 | $660 |
$1,000
42,790
kWh
|
$1,050
-
kW-mo/yr
|
- | $(-780.0) | - | - | |
03 | 3.8125: Remove rollers from the machines and clean in a closed solvent cleaner | $2,250 | $1,100 | - | - | - | $1,900 | $350 | - | |
04 | 3.6192: Use a less expensive method of waste removal | $170 | - | - | - |
$190
-
lb
|
- | $(-20.0) | - | |
05 | 4.112: Replace old machine with new automatic multi-station tool | $80,060 | $200,000 | - | - | - | $80,060 | - | - | |
06 | 4.321: Optimize production lot sizes and inventories | $29,130 | $30,000 | - | - | - | $(-40,000.0) | - | $69,130 | |
TOTAL RECOMMENDED | $115,040 | $236,760 |
$1,000
42,790
kWh
|
$3,210
-
kW-mo/yr
|
$190
-
lb
|
$41,180 | $330 | $69,130 | ||
TOTAL IMPLEMENTED | $83,490 | $205,660 |
$1,000
42,790
kWh
|
$3,210
-
kW-mo/yr
|
- | $79,280 | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs