ITAC Assessment: CO0447
ITAC logo
ITAC Assessment: CO0447
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product kitchen & bath cabinets
NAICS
n/a
SIC 2434: Wood Kitchen Cabinets
Sales Range $5
M
to 10
M
# of Employees 100
Plant Area 38,440
ft2
Annual Production 32,000
pieces
Production Hrs. Annual 4,420
hrs
Location (State) Wyoming

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $14,553 632,474
kWh
Electricity Demand $16,572 1,840
kW-mo/yr
Electricity Fees $300 -
Natural Gas $6,757 1,776
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $115,040 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $83,490

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Primary Product Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $2,160 $5,000 - $2,160
-
kW-mo/yr
- - - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,270 $660 $1,000
42,790
kWh
$1,050
-
kW-mo/yr
- $(-780.0) - -
03 3.8125: Remove rollers from the machines and clean in a closed solvent cleaner $2,250 $1,100 - - - $1,900 $350 -
04 3.6192: Use a less expensive method of waste removal $170 - - - $190
-
lb
- $(-20.0) -
05 4.112: Replace old machine with new automatic multi-station tool $80,060 $200,000 - - - $80,060 - -
06 4.321: Optimize production lot sizes and inventories $29,130 $30,000 - - - $(-40,000.0) - $69,130
TOTAL RECOMMENDED $115,040 $236,760 $1,000
42,790
kWh
$3,210
-
kW-mo/yr
$190
-
lb
$41,180 $330 $69,130
TOTAL IMPLEMENTED $83,490 $205,660 $1,000
42,790
kWh
$3,210
-
kW-mo/yr
- $79,280 - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs