| Assessment Year | 2000 |
|---|---|
| Principal Product | Towels |
| NAICS |
n/a
|
| SIC | 2211: Broadwoven Fabric Mills, Cotton |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
105,000
ft2
|
| Annual Production | 7,055,116
lb
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $162,157 | 5,405,231 |
kWh
|
$0.030 |
| Electricity Demand | $132,757 | 11,673 |
kW-mo/yr
|
$11.37 |
| Electricity Fees | $31,731 | - |
|
- |
| Natural Gas | $272,877 | 74,306 |
MMBtu
|
$3.67 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $183,692 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,877 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1113: Reduce combustion air flow to optimum | $37,979 | $10,000 | - | - | - |
$37,979
-
MMBtu
|
- | - | - | - | - | |
| 02 | 3.4116: Meter recycled water (to reduce sewer charges) | $6,635 | $8,000 | - | - | - | - | - | - | - | $6,635 | - | |
| 03 | 3.4151: Minimize water usage | $1,457 | $300 | - | - | - | - |
$619
-
Tgal
|
- | - | - |
$838
-
Tgal
|
|
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,420 | - |
$1,471
49,041
kWh
|
$791
-
kW-mo/yr
|
$158 | - | - | - | - | - | - | |
| 05 | 3.5217: Reuse / recycle/ sell paper products | $3,265 | - | - | - | - | - | - |
$3,265
-
lb
|
- | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,784 | $16,840 |
$4,042
134,720
kWh
|
$2,193
-
kW-mo/yr
|
$549 | - | - | - | - | - | - | |
| 07 | 2.4133: Use most efficient type of electric motors | $5,152 | $44,647 |
$2,774
92,463
kWh
|
$1,914
-
kW-mo/yr
|
$464 | - | - | - | - | - | - | |
| 08 | 4.111: Add equipment/ operators to reduce production bottleneck | $120,000 | $700,000 | - | - | - | - | - | - | $120,000 | - | - | |
| TOTAL RECOMMENDED | $183,692 | $779,787 |
$8,287
276,224
kWh
|
$4,898
-
kW-mo/yr
|
$1,171 |
$37,979
-
MMBtu
|
$619
-
Tgal
|
$3,265
-
lb
|
$120,000 | $6,635 |
$838
-
Tgal
|
||
| TOTAL IMPLEMENTED | $3,877 | $300 |
$1,471
49,041
kWh
|
$791
-
kW-mo/yr
|
$158 | - |
$619
-
Tgal
|
- | - | - |
$838
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs