Assessment Year | 2000 |
---|---|
Principal Product | Cereal and Snack Foods |
NAICS |
n/a
|
SIC | 2043: Cereal Breakfast Foods |
Sales Range | greater than $500 M |
# of Employees | 200 |
Plant Area |
650,000
ft2
|
Annual Production | 23,000,000
pieces
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,050,086 | 64,700,335 |
kWh
|
$0.016 |
Electricity Demand | $1,106,811 | 98,226 |
kW-mo/yr
|
$11.27 |
Electricity Fees | $153,686 | - |
|
- |
Natural Gas | $1,600,447 | 404,145 |
MMBtu
|
$3.96 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $107,395 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,855 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2421: Install waste heat boiler to provide direct power | $2,459 | - | - | - | - |
$2,459
-
MMBtu
|
- | - | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $14,855 | $30,000 |
$2,294
141,347
kWh
|
$2,287
-
kW-mo/yr
|
$274 | - | - | $10,000 | - | - | |
03 | 3.4111: Use closed cycle process to minimize waste water production | $11,854 | $3,000 | - | - | - | - |
$6,078
-
Tgal
|
- | - |
$5,776
-
Tgal
|
|
04 | 3.4116: Meter recycled water (to reduce sewer charges) | $42,350 | $8,000 | - | - | - | - | - | - | $42,350 | - | |
05 | 2.4134: Replace electric motor with fossil fuel engine | $17,878 | $40,000 |
$2,473
152,374
kWh
|
$20,475
-
kW-mo/yr
|
$1,377 |
$(-6,447.0)
-
MMBtu
|
- | - | - | - | |
06 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $10,968 | - | - |
$10,347
-
kW-mo/yr
|
$621 | - | - | - | - | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $7,031 | - |
$3,408
209,991
kWh
|
$3,225
-
kW-mo/yr
|
$398 | - | - | - | - | - | |
TOTAL RECOMMENDED | $107,395 | $81,000 |
$8,175
503,712
kWh
|
$36,334
-
kW-mo/yr
|
$2,670 |
$(-3,988.0)
-
MMBtu
|
$6,078
-
Tgal
|
$10,000 | $42,350 |
$5,776
-
Tgal
|
||
TOTAL IMPLEMENTED | $14,855 | $30,000 |
$2,294
141,347
kWh
|
$2,287
-
kW-mo/yr
|
$274 | - | - | $10,000 | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs