ITAC Assessment: GT0703
ITAC logo
ITAC Assessment: GT0703
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Cereal and Snack Foods
NAICS
n/a
SIC 2043: Cereal Breakfast Foods
Sales Range greater than $500
M
# of Employees 200
Plant Area 650,000
ft2
Annual Production 23,000,000
pieces
Production Hrs. Annual 8,400
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,050,086 64,700,335
kWh
Electricity Demand $1,106,811 98,226
kW-mo/yr
Electricity Fees $153,686 -
Natural Gas $1,600,447 404,145
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $107,395 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,855

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Water Consumption Savings
01 2.2421: Install waste heat boiler to provide direct power $2,459 - - - - $2,459
-
MMBtu
- - - -
02 2.4133: Use most efficient type of electric motors $14,855 $30,000 $2,294
141,347
kWh
$2,287
-
kW-mo/yr
$274 - - $10,000 - -
03 3.4111: Use closed cycle process to minimize waste water production $11,854 $3,000 - - - - $6,078
-
Tgal
- - $5,776
-
Tgal
04 3.4116: Meter recycled water (to reduce sewer charges) $42,350 $8,000 - - - - - - $42,350 -
05 2.4134: Replace electric motor with fossil fuel engine $17,878 $40,000 $2,473
152,374
kWh
$20,475
-
kW-mo/yr
$1,377 $(-6,447.0)
-
MMBtu
- - - -
06 2.3131: Reschedule plant operations or reduce load to avoid peaks $10,968 - - $10,347
-
kW-mo/yr
$621 - - - - -
07 2.4231: Reduce the pressure of compressed air to the minimum required $7,031 - $3,408
209,991
kWh
$3,225
-
kW-mo/yr
$398 - - - - -
TOTAL RECOMMENDED $107,395 $81,000 $8,175
503,712
kWh
$36,334
-
kW-mo/yr
$2,670 $(-3,988.0)
-
MMBtu
$6,078
-
Tgal
$10,000 $42,350 $5,776
-
Tgal
TOTAL IMPLEMENTED $14,855 $30,000 $2,294
141,347
kWh
$2,287
-
kW-mo/yr
$274 - - $10,000 - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs