ITAC Assessment: GT0701
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Carpet Coatings
NAICS
n/a
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 45
Plant Area 99,000
ft2
Annual Production 58,500,000
thousand feet
Production Hrs. Annual 4,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $33,451 1,115,040
kWh
Electricity Demand $153,186 11,272
kW-mo/yr
Electricity Fees $11,198 -
Natural Gas $31,853 5,146
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $113,150 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $36,484

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 2.4239: Eliminate or reduce compressed air usage $11,490 $5,000 $5,036
167,850
kWh
$5,804
-
kW-mo/yr
$650 - - - -
02 2.1113: Reduce combustion air flow to optimum $23,600 $2,200 - - - $23,600
-
MMBtu
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $3,842 $9,456 $1,638
54,596
kWh
$2,105
-
kW-mo/yr
$99 - - - -
04 2.4133: Use most efficient type of electric motors $3,420 $25,117 $1,522
50,740
kWh
$1,821
-
kW-mo/yr
$77 - - - -
05 3.5311: Recover and reuse waste material $2,219 - - - - - $2,219
-
lb
- -
06 3.5315: Lease / purchase baler; sell cardboard to recycler $30,845 - - - - - - - $30,845
07 2.7233: Use properly designed and sized hvac equipment $36,500 $28,000 - - - $6,500
-
MMBtu
- $30,000 -
08 2.2511: Insulate bare equipment $1,234 $2,999 - - - $1,234
-
MMBtu
- - -
TOTAL RECOMMENDED $113,150 $72,772 $8,196
273,186
kWh
$9,730
-
kW-mo/yr
$826 $31,334
-
MMBtu
$2,219
-
lb
$30,000 $30,845
TOTAL IMPLEMENTED $36,484 $25,117 $1,522
50,740
kWh
$1,821
-
kW-mo/yr
$77 - $2,219
-
lb
- $30,845
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs