Assessment Year | 2000 |
---|---|
Principal Product | Carpet Coatings |
NAICS |
n/a
|
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 45 |
Plant Area |
99,000
ft2
|
Annual Production | 58,500,000
thousand feet
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $33,451 | 1,115,040 |
kWh
|
$0.030 |
Electricity Demand | $153,186 | 11,272 |
kW-mo/yr
|
$13.59 |
Electricity Fees | $11,198 | - |
|
- |
Natural Gas | $31,853 | 5,146 |
MMBtu
|
$6.19 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $113,150 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $36,484 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4239: Eliminate or reduce compressed air usage | $11,490 | $5,000 |
$5,036
167,850
kWh
|
$5,804
-
kW-mo/yr
|
$650 | - | - | - | - | |
02 | 2.1113: Reduce combustion air flow to optimum | $23,600 | $2,200 | - | - | - |
$23,600
-
MMBtu
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,842 | $9,456 |
$1,638
54,596
kWh
|
$2,105
-
kW-mo/yr
|
$99 | - | - | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $3,420 | $25,117 |
$1,522
50,740
kWh
|
$1,821
-
kW-mo/yr
|
$77 | - | - | - | - | |
05 | 3.5311: Recover and reuse waste material | $2,219 | - | - | - | - | - |
$2,219
-
lb
|
- | - | |
06 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $30,845 | - | - | - | - | - | - | - | $30,845 | |
07 | 2.7233: Use properly designed and sized hvac equipment | $36,500 | $28,000 | - | - | - |
$6,500
-
MMBtu
|
- | $30,000 | - | |
08 | 2.2511: Insulate bare equipment | $1,234 | $2,999 | - | - | - |
$1,234
-
MMBtu
|
- | - | - | |
TOTAL RECOMMENDED | $113,150 | $72,772 |
$8,196
273,186
kWh
|
$9,730
-
kW-mo/yr
|
$826 |
$31,334
-
MMBtu
|
$2,219
-
lb
|
$30,000 | $30,845 | ||
TOTAL IMPLEMENTED | $36,484 | $25,117 |
$1,522
50,740
kWh
|
$1,821
-
kW-mo/yr
|
$77 | - |
$2,219
-
lb
|
- | $30,845 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs