ITAC Assessment: GT0700
ITAC logo
ITAC Assessment: GT0700
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Wood Processing
NAICS
n/a
SIC 2491: Wood Preserving
Sales Range $10
M
to 50
M
# of Employees 46
Plant Area 100,000
ft2
Annual Production 25,000
thousand feet
Production Hrs. Annual 2,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $40,971 1,014,068
kWh
Electricity Demand $36,456 3,255
kW-mo/yr
Electricity Fees $5,710 -
Natural Gas $101,146 26,877
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $260,767 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,806

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings Increase in Production Savings
01 2.8112: Combine utility meters $2,238 $5,018 - - $2,238 - - - -
02 2.8114: Change rate schedules or other changes in utility service $193 $330 - - $193 - - - -
03 2.1233: Analyze flue gas for proper air/fuel ratio $170 - - - - $170
-
MMBtu
- - -
04 2.7124: Make a practice of turning off lights when not needed $715 $2,240 $330
8,206
kWh
$280
-
kW-mo/yr
$105 - - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $530 $675 $230
5,862
kWh
$246
-
kW-mo/yr
$54 - - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,105 $4,013 $401
9,965
kWh
$627
-
kW-mo/yr
$77 - - - -
07 2.4133: Use most efficient type of electric motors $2,576 $15,200 $1,566
38,687
kWh
$840
-
kW-mo/yr
$170 - - - -
08 3.4155: Meter waste water $2,620 $500 - - - - - $2,620 -
09 3.5212: Regrind, reuse, or sell scrap plastic parts $620 $2,490 - - - - $210
-
lb
$410 -
10 4.111: Add equipment/ operators to reduce production bottleneck $250,000 $180,000 - - - - - - $250,000
TOTAL RECOMMENDED $260,767 $210,466 $2,527
62,720
kWh
$1,993
-
kW-mo/yr
$2,837 $170
-
MMBtu
$210
-
lb
$3,030 $250,000
TOTAL IMPLEMENTED $7,806 $24,443 $2,297
56,858
kWh
$1,747
-
kW-mo/yr
$352 $170
-
MMBtu
$210
-
lb
$3,030 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs