| Assessment Year | 2000 |
|---|---|
| Principal Product | Wood Processing |
| NAICS |
n/a
|
| SIC | 2491: Wood Preserving |
| Sales Range | $10 M to 50M |
| # of Employees | 46 |
| Plant Area |
100,000
ft2
|
| Annual Production | 25,000
thousand feet
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $40,971 | 1,014,068 |
kWh
|
$0.040 |
| Electricity Demand | $36,456 | 3,255 |
kW-mo/yr
|
$11.20 |
| Electricity Fees | $5,710 | - |
|
- |
| Natural Gas | $101,146 | 26,877 |
MMBtu
|
$3.76 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $260,767 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,806 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8112: Combine utility meters | $2,238 | $5,018 | - | - | $2,238 | - | - | - | - | |
| 02 | 2.8114: Change rate schedules or other changes in utility service | $193 | $330 | - | - | $193 | - | - | - | - | |
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $170 | - | - | - | - |
$170
-
MMBtu
|
- | - | - | |
| 04 | 2.7124: Make a practice of turning off lights when not needed | $715 | $2,240 |
$330
8,206
kWh
|
$280
-
kW-mo/yr
|
$105 | - | - | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $530 | $675 |
$230
5,862
kWh
|
$246
-
kW-mo/yr
|
$54 | - | - | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,105 | $4,013 |
$401
9,965
kWh
|
$627
-
kW-mo/yr
|
$77 | - | - | - | - | |
| 07 | 2.4133: Use most efficient type of electric motors | $2,576 | $15,200 |
$1,566
38,687
kWh
|
$840
-
kW-mo/yr
|
$170 | - | - | - | - | |
| 08 | 3.4155: Meter waste water | $2,620 | $500 | - | - | - | - | - | $2,620 | - | |
| 09 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $620 | $2,490 | - | - | - | - |
$210
-
lb
|
$410 | - | |
| 10 | 4.111: Add equipment/ operators to reduce production bottleneck | $250,000 | $180,000 | - | - | - | - | - | - | $250,000 | |
| TOTAL RECOMMENDED | $260,767 | $210,466 |
$2,527
62,720
kWh
|
$1,993
-
kW-mo/yr
|
$2,837 |
$170
-
MMBtu
|
$210
-
lb
|
$3,030 | $250,000 | ||
| TOTAL IMPLEMENTED | $7,806 | $24,443 |
$2,297
56,858
kWh
|
$1,747
-
kW-mo/yr
|
$352 |
$170
-
MMBtu
|
$210
-
lb
|
$3,030 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs