ITAC Assessment: GT0698
ITAC logo
ITAC Assessment: GT0698
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Stator and Rotor Coils
NAICS
n/a
SIC 3311:
Sales Range $100
M
to 500
M
# of Employees 305
Plant Area 160,000
ft2
Annual Production 11,000
pieces
Production Hrs. Annual 8,650
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $271,146 10,002,638
kWh
Electricity Demand $202,127 20,069
kW-mo/yr
Electricity Fees $19,720 -
Natural Gas $70,878 15,215
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $314,371 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $69,227

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Fuel Oil #1 Savings Personnel Changes Savings
01 2.2511: Insulate bare equipment $7,360 $3,240 $7,360
272,567
kWh
- - - - -
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $85,596 $65,000 $40,601
1,503,517
kWh
$74,736
-
kW-mo/yr
- $(-29,741.0)
-
MMBtu
- -
03 2.7124: Make a practice of turning off lights when not needed $1,389 $250 $651
24,033
kWh
$685
-
kW-mo/yr
$53 - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $422 $192 $253
9,379
kWh
$135
-
kW-mo/yr
$16 - - $18
05 4.111: Add equipment/ operators to reduce production bottleneck $108,000 $160,000 - - - - - $108,000
06 2.7232: Replace existing hvac unit with high efficiency model $59,243 $300,000 $17,280
639,801
kWh
$16,608
-
kW-mo/yr
$1,355 - - $24,000
07 2.7224: Reduce space conditioning during non-working hours $1,235 $1,800 $1,188
43,962
kWh
- $47 - - -
08 2.2437: Recover waste heat from equipment $29,275 $55,000 - - - $29,275
-
MMBtu
- -
09 3.5111: Filter and reuse hydraulic oil $3,712 $6,200 - - - - $3,712
-
MMBtu
-
10 2.2524: Avoid cooling of process streams or materials that must subsequently be heated $18,139 $77,275 $17,442
645,955
kWh
- $697 - - -
TOTAL RECOMMENDED $314,371 $668,957 $84,775
3,139,214
kWh
$92,164
-
kW-mo/yr
$2,168 $(-466.0)
-
MMBtu
$3,712
-
MMBtu
$132,018
TOTAL IMPLEMENTED $69,227 $305,290 $26,479
980,363
kWh
$17,293
-
kW-mo/yr
$1,455 - - $24,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Fuel Oil #1 Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs