Assessment Year | 2000 |
---|---|
Principal Product | Stator and Rotor Coils |
NAICS |
n/a
|
SIC | 3311: |
Sales Range | $100 M to 500M |
# of Employees | 305 |
Plant Area |
160,000
ft2
|
Annual Production | 11,000
pieces
|
Production Hrs. Annual | 8,650
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $271,146 | 10,002,638 |
kWh
|
$0.027 |
Electricity Demand | $202,127 | 20,069 |
kW-mo/yr
|
$10.07 |
Electricity Fees | $19,720 | - |
|
- |
Natural Gas | $70,878 | 15,215 |
MMBtu
|
$4.66 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $314,371 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $69,227 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Fuel Oil #1 Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $7,360 | $3,240 |
$7,360
272,567
kWh
|
- | - | - | - | - | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $85,596 | $65,000 |
$40,601
1,503,517
kWh
|
$74,736
-
kW-mo/yr
|
- |
$(-29,741.0)
-
MMBtu
|
- | - | |
03 | 2.7124: Make a practice of turning off lights when not needed | $1,389 | $250 |
$651
24,033
kWh
|
$685
-
kW-mo/yr
|
$53 | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $422 | $192 |
$253
9,379
kWh
|
$135
-
kW-mo/yr
|
$16 | - | - | $18 | |
05 | 4.111: Add equipment/ operators to reduce production bottleneck | $108,000 | $160,000 | - | - | - | - | - | $108,000 | |
06 | 2.7232: Replace existing hvac unit with high efficiency model | $59,243 | $300,000 |
$17,280
639,801
kWh
|
$16,608
-
kW-mo/yr
|
$1,355 | - | - | $24,000 | |
07 | 2.7224: Reduce space conditioning during non-working hours | $1,235 | $1,800 |
$1,188
43,962
kWh
|
- | $47 | - | - | - | |
08 | 2.2437: Recover waste heat from equipment | $29,275 | $55,000 | - | - | - |
$29,275
-
MMBtu
|
- | - | |
09 | 3.5111: Filter and reuse hydraulic oil | $3,712 | $6,200 | - | - | - | - |
$3,712
-
MMBtu
|
- | |
10 | 2.2524: Avoid cooling of process streams or materials that must subsequently be heated | $18,139 | $77,275 |
$17,442
645,955
kWh
|
- | $697 | - | - | - | |
TOTAL RECOMMENDED | $314,371 | $668,957 |
$84,775
3,139,214
kWh
|
$92,164
-
kW-mo/yr
|
$2,168 |
$(-466.0)
-
MMBtu
|
$3,712
-
MMBtu
|
$132,018 | ||
TOTAL IMPLEMENTED | $69,227 | $305,290 |
$26,479
980,363
kWh
|
$17,293
-
kW-mo/yr
|
$1,455 | - | - | $24,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Fuel Oil #1 Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs