ITAC Assessment: GT0697
ITAC logo
ITAC Assessment: GT0697
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Furniture
NAICS
n/a
SIC 2511: Wood Household Furniture, Except Upholstered
Sales Range $10
M
to 50
M
# of Employees 380
Plant Area 45,900
ft2
Annual Production 100,000
pieces
Production Hrs. Annual 2,083
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $262,393 7,553,050
kWh
Electricity Demand $219,462 26,346
kW-mo/yr
Electricity Fees $35,990 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $116,105 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $70,947

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $6,385 $46,235 $2,639
75,956
kWh
$3,233
-
kW-mo/yr
$513 - - -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,208 $4,355 $1,504
43,295
kWh
$1,431
-
kW-mo/yr
$273 - - -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $31,700 $37,500 $18,994
546,750
kWh
$10,396
-
kW-mo/yr
$2,310 - - -
04 4.126: Install sensors to detect defects $38,825 $600 - - - $35,625 $1,200 $2,000
05 3.1191: Change procedures / equipment / operating conditions $5,825 $2,850 - - - $2,850 $2,975 -
06 2.4133: Use most efficient type of electric motors $1,480 $26,340 $586
16,873
kWh
$677
-
kW-mo/yr
$217 - - -
07 4.513: Re-arrange equipment layout to reduce labor costs $19,000 $3,800 - - - $19,000 - -
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,770 $900 $3,473
99,957
kWh
$4,579
-
kW-mo/yr
$718 - - -
09 2.6218: Turn off equipment when not in use $912 $2,880 $862
24,800
kWh
- $50 - - -
TOTAL RECOMMENDED $116,105 $125,460 $28,058
807,631
kWh
$20,316
-
kW-mo/yr
$4,081 $57,475 $4,175 $2,000
TOTAL IMPLEMENTED $70,947 $56,365 $3,501
100,756
kWh
$3,233
-
kW-mo/yr
$563 $57,475 $4,175 $2,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs