ITAC Assessment: GT0686
ITAC logo
ITAC Assessment: GT0686
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Dyed Carpet
NAICS
n/a
SIC 2273: Carpets and Rugs
Sales Range $5
M
to 10
M
# of Employees 52
Plant Area 50,000
ft2
Annual Production 36,238,500
thousand feet
Production Hrs. Annual 5,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $68,425 2,616,647
kWh
Electricity Demand $138,113 9,263
kW-mo/yr
Electricity Fees $3,614 -
Natural Gas $203,732 71,192
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $114,463 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $95,538

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.8114: Change rate schedules or other changes in utility service $74,340 - - - - - - - $74,340 -
02 2.6218: Turn off equipment when not in use $1,980 - $1,980
75,615
kWh
- - - - - - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,607 $700 $1,826
69,754
kWh
$2,504
-
kW-mo/yr
$1,277 - - - - -
04 2.2511: Insulate bare equipment $1,400 $500 - - - $1,335
-
MMBtu
- - - $65
05 2.2511: Insulate bare equipment $1,280 $1,105 - - - $1,280
-
MMBtu
- - - -
06 2.2511: Insulate bare equipment $4,025 $9,895 - - - $4,025
-
MMBtu
- - - -
07 4.111: Add equipment/ operators to reduce production bottleneck $7,650 $17,105 - - - - - $7,650 - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $1,990 $2,430 $863
33,118
kWh
$1,127
-
kW-mo/yr
- - - - - -
09 2.4133: Use most efficient type of electric motors $10,132 $49,180 $3,678
140,680
kWh
$6,043
-
kW-mo/yr
$411 - - - - -
10 2.4111: Utilize energy-efficient belts and other improved mechanisms $789 $944 $342
13,189
kWh
$447
-
kW-mo/yr
- - - - - -
11 3.5217: Reuse / recycle/ sell paper products $540 - - - - - $540
-
lb
- - -
12 3.6192: Use a less expensive method of waste removal $4,730 - - - - - - - $4,730 -
TOTAL RECOMMENDED $114,463 $81,859 $8,689
332,356
kWh
$10,121
-
kW-mo/yr
$1,688 $6,640
-
MMBtu
$540
-
lb
$7,650 $79,070 $65
TOTAL IMPLEMENTED $95,538 $54,859 $6,709
256,741
kWh
$10,121
-
kW-mo/yr
$1,688 $2,615
-
MMBtu
- - $74,340 $65
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs