Assessment Year | 2000 |
---|---|
Principal Product | Dyed Carpet |
NAICS |
n/a
|
SIC | 2273: Carpets and Rugs |
Sales Range | $5 M to 10M |
# of Employees | 52 |
Plant Area |
50,000
ft2
|
Annual Production | 36,238,500
thousand feet
|
Production Hrs. Annual | 5,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $68,425 | 2,616,647 |
kWh
|
$0.026 |
Electricity Demand | $138,113 | 9,263 |
kW-mo/yr
|
$14.91 |
Electricity Fees | $3,614 | - |
|
- |
Natural Gas | $203,732 | 71,192 |
MMBtu
|
$2.86 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $114,463 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $95,538 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $74,340 | - | - | - | - | - | - | - | $74,340 | - | |
02 | 2.6218: Turn off equipment when not in use | $1,980 | - |
$1,980
75,615
kWh
|
- | - | - | - | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,607 | $700 |
$1,826
69,754
kWh
|
$2,504
-
kW-mo/yr
|
$1,277 | - | - | - | - | - | |
04 | 2.2511: Insulate bare equipment | $1,400 | $500 | - | - | - |
$1,335
-
MMBtu
|
- | - | - | $65 | |
05 | 2.2511: Insulate bare equipment | $1,280 | $1,105 | - | - | - |
$1,280
-
MMBtu
|
- | - | - | - | |
06 | 2.2511: Insulate bare equipment | $4,025 | $9,895 | - | - | - |
$4,025
-
MMBtu
|
- | - | - | - | |
07 | 4.111: Add equipment/ operators to reduce production bottleneck | $7,650 | $17,105 | - | - | - | - | - | $7,650 | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,990 | $2,430 |
$863
33,118
kWh
|
$1,127
-
kW-mo/yr
|
- | - | - | - | - | - | |
09 | 2.4133: Use most efficient type of electric motors | $10,132 | $49,180 |
$3,678
140,680
kWh
|
$6,043
-
kW-mo/yr
|
$411 | - | - | - | - | - | |
10 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $789 | $944 |
$342
13,189
kWh
|
$447
-
kW-mo/yr
|
- | - | - | - | - | - | |
11 | 3.5217: Reuse / recycle/ sell paper products | $540 | - | - | - | - | - |
$540
-
lb
|
- | - | - | |
12 | 3.6192: Use a less expensive method of waste removal | $4,730 | - | - | - | - | - | - | - | $4,730 | - | |
TOTAL RECOMMENDED | $114,463 | $81,859 |
$8,689
332,356
kWh
|
$10,121
-
kW-mo/yr
|
$1,688 |
$6,640
-
MMBtu
|
$540
-
lb
|
$7,650 | $79,070 | $65 | ||
TOTAL IMPLEMENTED | $95,538 | $54,859 |
$6,709
256,741
kWh
|
$10,121
-
kW-mo/yr
|
$1,688 |
$2,615
-
MMBtu
|
- | - | $74,340 | $65 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs