Assessment Year | 2000 |
---|---|
Principal Product | Yarn |
NAICS |
n/a
|
SIC | 2273: Carpets and Rugs |
Sales Range | $10 M to 50M |
# of Employees | 170 |
Plant Area |
160,000
ft2
|
Annual Production | 9,736,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $129,285 | 5,582,356 |
kWh
|
$0.023 |
Electricity Demand | $52,860 | 15,648 |
kW-mo/yr
|
$3.38 |
Electricity Fees | $10,930 | - |
|
- |
Natural Gas | $104,755 | 22,427 |
MMBtu
|
$4.67 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $144,411 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $39,697 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $48,133 | $1,000 | - | - | - | - | - | - | $48,133 | - | - | |
02 | 4.125: | $36,150 | $145,000 | - | - | - | - | - | $25,000 | - | $11,150 | - | |
03 | 3.4111: Use closed cycle process to minimize waste water production | $16,620 | $10,500 | - |
$708
-
kW-mo/yr
|
- |
$11,524
-
Tgal
|
- | - | - | $(-1,300.0) |
$5,688
-
Tgal
|
|
04 | 2.2437: Recover waste heat from equipment | $12,474 | $45,900 | - | - |
$10,134
-
MMBtu
|
$1,190
-
Tgal
|
$551
-
gal
|
- | - | - |
$599
-
Tgal
|
|
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,829 | $300 |
$6,829
273,154
kWh
|
- | - | - | - | - | - | - | - | |
06 | 2.7122: Disconnect ballasts | $651 | $1,612 |
$484
19,343
kWh
|
$167
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,239 | - |
$2,708
108,441
kWh
|
$531
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
08 | 2.2414: Use waste heat from hot flue gases to preheat | $14,071 | $42,000 | - | - |
$14,071
-
MMBtu
|
- | - | - | - | - | - | |
09 | 2.4133: Use most efficient type of electric motors | $4,260 | $120,000 |
$3,050
121,923
kWh
|
$1,210
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
10 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $1,128 | $2,400 |
$838
33,411
kWh
|
$290
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
11 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $856 | $490 |
$600
24,033
kWh
|
$256
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
TOTAL RECOMMENDED | $144,411 | $369,202 |
$14,509
580,305
kWh
|
$3,162
-
kW-mo/yr
|
$24,205
-
MMBtu
|
$12,714
-
Tgal
|
$551
-
gal
|
$25,000 | $48,133 | $9,850 |
$6,287
-
Tgal
|
||
TOTAL IMPLEMENTED | $39,697 | $174,602 |
$6,842
273,740
kWh
|
$2,872
-
kW-mo/yr
|
$14,071
-
MMBtu
|
$11,524
-
Tgal
|
- | - | - | $(-1,300.0) |
$5,688
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs