Assessment Year | 1999 |
---|---|
Principal Product | Dyed Yarn |
NAICS |
n/a
|
SIC | 2269: Finishers of Textiles, Not elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
85,000
ft2
|
Annual Production | 13,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $70,187 | 3,147,421 |
kWh
|
$0.022 |
Electricity Demand | $100,454 | 6,611 |
kW-mo/yr
|
$15.19 |
Electricity Fees | $14,915 | - |
|
- |
Natural Gas | $407,981 | 97,768 |
MMBtu
|
$4.17 |
Fuel Oil #2 | $49,007 | 15,567 |
MMBtu
|
$3.15 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $224,057 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Fuel Oil #2 Savings | Water Disposal Savings | Administrative Changes Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1331: Burn a less expensive grade of fuel | $103,610 | $28,000 | - | - |
$390,080
-
MMBtu
|
$(-286,470.0)
-
MMBtu
|
- | - | - | |
02 | 2.8112: Combine utility meters | $2,970 | - | - | - | - | - | - | $2,970 | - | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $20,745 | $900 | - | - |
$20,745
-
MMBtu
|
- | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,420 | $600 |
$6,420
107,268
kWh
|
- | - | - | - | - | - | |
05 | 2.2135: Repair and eliminate steam leaks | $1,840 | $600 | - | - |
$1,780
-
MMBtu
|
- |
$60
-
Tgal
|
- | - | |
06 | 3.4111: Use closed cycle process to minimize waste water production | $900 | $1,040 | - | - |
$900
-
MMBtu
|
- | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,872 | $20,086 |
$8,739
148,007
kWh
|
$133 | - | - | - | - | - | |
08 | 3.4111: Use closed cycle process to minimize waste water production | $63,700 | $96,450 | - | - |
$46,040
-
MMBtu
|
- |
$17,660
-
Tgal
|
- | - | |
09 | 4.114: Add/modify equipment to improve drying process | $15,000 | $70,000 | - | - | - | - | - | - | $15,000 | |
TOTAL RECOMMENDED | $224,057 | $217,676 |
$15,159
255,275
kWh
|
$133 |
$459,545
-
MMBtu
|
$(-286,470.0)
-
MMBtu
|
$17,720
-
Tgal
|
$2,970 | $15,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Fuel Oil #2 Savings | Water Disposal Savings | Administrative Changes Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs