ITAC Assessment: GT0671
ITAC logo
ITAC Assessment: GT0671
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Dyed Yarn
NAICS
n/a
SIC 2269: Finishers of Textiles, Not elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 85,000
ft2
Annual Production 13,000,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $70,187 3,147,421
kWh
Electricity Demand $100,454 6,611
kW-mo/yr
Electricity Fees $14,915 -
Natural Gas $407,981 97,768
MMBtu
Fuel Oil #2 $49,007 15,567
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $224,057 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Fuel Oil #2 Savings Water Disposal Savings Administrative Changes Savings Primary Product Savings
01 2.1331: Burn a less expensive grade of fuel $103,610 $28,000 - - $390,080
-
MMBtu
$(-286,470.0)
-
MMBtu
- - -
02 2.8112: Combine utility meters $2,970 - - - - - - $2,970 -
03 2.1233: Analyze flue gas for proper air/fuel ratio $20,745 $900 - - $20,745
-
MMBtu
- - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,420 $600 $6,420
107,268
kWh
- - - - - -
05 2.2135: Repair and eliminate steam leaks $1,840 $600 - - $1,780
-
MMBtu
- $60
-
Tgal
- -
06 3.4111: Use closed cycle process to minimize waste water production $900 $1,040 - - $900
-
MMBtu
- - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $8,872 $20,086 $8,739
148,007
kWh
$133 - - - - -
08 3.4111: Use closed cycle process to minimize waste water production $63,700 $96,450 - - $46,040
-
MMBtu
- $17,660
-
Tgal
- -
09 4.114: Add/modify equipment to improve drying process $15,000 $70,000 - - - - - - $15,000
TOTAL RECOMMENDED $224,057 $217,676 $15,159
255,275
kWh
$133 $459,545
-
MMBtu
$(-286,470.0)
-
MMBtu
$17,720
-
Tgal
$2,970 $15,000
TOTAL IMPLEMENTED - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Fuel Oil #2 Savings Water Disposal Savings Administrative Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs