| Assessment Year | 1999 |
|---|---|
| Principal Product | carpet |
| NAICS |
n/a
|
| SIC | 2273: Carpets and Rugs |
| Sales Range | $10 M to 50M |
| # of Employees | 155 |
| Plant Area |
180,000
ft2
|
| Annual Production | 22,820
thousand feet
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $77,922 | 3,092,028 |
kWh
|
$0.025 |
| Electricity Demand | $166,298 | 11,143 |
kW-mo/yr
|
$14.92 |
| Electricity Fees | $10,221 | - |
|
- |
| Natural Gas | $50,096 | 14,252 |
MMBtu
|
$3.52 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $150,788 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $92,204 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8112: Combine utility meters | $512 | - | - | - | - | - | $512 | - | - | |
| 02 | 2.8114: Change rate schedules or other changes in utility service | $36,226 | - | - | - | - | - | $36,226 | - | - | |
| 03 | 2.8113: Purchase gas directly from a contract gas supplier | $370 | - | - | - | - | - | $370 | - | - | |
| 04 | 2.1123: Install automatic stack damper | $3,388 | $750 | - | - | - |
$3,388
-
MMBtu
|
- | - | - | |
| 05 | 2.4225: Install common header on compressors | $30,991 | $5,250 |
$905
36,049
kWh
|
$28,332
-
kW-mo/yr
|
$1,754 | - | - | - | - | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $10,078 | $15,000 |
$4,685
185,815
kWh
|
$4,887
-
kW-mo/yr
|
$506 | - | - | - | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,869 | $28,628 |
$2,477
98,183
kWh
|
$4,937
-
kW-mo/yr
|
$455 | - | - | - | - | |
| 08 | 2.4133: Use most efficient type of electric motors | $8,397 | $64,899 |
$3,719
147,714
kWh
|
$4,203
-
kW-mo/yr
|
$475 | - | - | - | - | |
| 09 | 3.5313: Increase amount of waste recovered for resale | $6,000 | $4,000 | - | - | - | - | - | $6,000 | - | |
| 10 | 4.454: Modify startup/shutdown times | $46,957 | - |
$11,843
469,812
kWh
|
- | $711 |
$10,778
-
MMBtu
|
- | - | $23,625 | |
| TOTAL RECOMMENDED | $150,788 | $118,527 |
$23,629
937,573
kWh
|
$42,359
-
kW-mo/yr
|
$3,901 |
$14,166
-
MMBtu
|
$37,108 | $6,000 | $23,625 | ||
| TOTAL IMPLEMENTED | $92,204 | $89,149 |
$9,309
369,578
kWh
|
$37,422
-
kW-mo/yr
|
$2,735 | - | $36,738 | $6,000 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs