| Assessment Year | 1999 |
|---|---|
| Principal Product | carpet |
| NAICS |
n/a
|
| SIC | 2269: Finishers of Textiles, Not elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 130 |
| Plant Area |
160,000
ft2
|
| Annual Production | 7,000,000
lb
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $27,448 | 1,332,943 |
kWh
|
$0.021 |
| Electricity Demand | $24,946 | 5,177 |
kW-mo/yr
|
$4.82 |
| Electricity Fees | $3,138 | - |
|
- |
| Natural Gas | $10,122 | 1,891 |
MMBtu
|
$5.35 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $75,910 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,454 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $122 | $350 |
$115
3,810
kWh
|
- | $7 | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $162 | $50 |
$153
5,862
kWh
|
- | $9 | - | - | |
| 03 | 2.2531: Re-size charging openings or add movable cover or door | $182 | - |
$172
6,448
kWh
|
- | $10 | - | - | |
| 04 | 2.2621: Modify refrigeration system to operate at a lower pressure | $62 | $200 |
$58
2,345
kWh
|
- | $4 | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,292 | $18,568 |
$4,554
174,971
kWh
|
$1,382
-
kW-mo/yr
|
$356 | - | - | |
| 06 | 4.423: Move product using mechanical means | $52,560 | $8,050 | - | - | - | - | $52,560 | |
| 07 | 4.441: Install automatic packing equipment | $1,740 | $1,719 | - | - | - | - | $1,740 | |
| 08 | 3.5313: Increase amount of waste recovered for resale | $14,790 | - | - | - | - |
$14,790
-
lb
|
- | |
| TOTAL RECOMMENDED | $75,910 | $28,937 |
$5,052
193,436
kWh
|
$1,382
-
kW-mo/yr
|
$386 |
$14,790
-
lb
|
$54,300 | ||
| TOTAL IMPLEMENTED | $6,454 | $18,618 |
$4,707
180,833
kWh
|
$1,382
-
kW-mo/yr
|
$365 | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs