Assessment Year | 1999 |
---|---|
Principal Product | Gypsum Wallboard |
NAICS |
n/a
|
SIC | 3275: Gypsum Products |
Sales Range | $50 M to 100M |
# of Employees | 96 |
Plant Area |
600,000
ft2
|
Annual Production | 362,000
thousand feet
|
Production Hrs. Annual | 8,272
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $548,479 | 19,430,833 |
kWh
|
$0.028 |
Electricity Demand | $286,545 | 32,562 |
kW-mo/yr
|
$8.80 |
Electricity Fees | $18,882 | - |
|
- |
Natural Gas | $2,576,743 | 824,797 |
MMBtu
|
$3.12 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $545,717 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $452,161 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $30,744 | $35,000 | - | - | - | - | - | $30,744 | |
02 | 2.1133: Adjust burners for efficient operation | $366,782 | $180,000 | - | - | - |
$366,782
-
MMBtu
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,440 | $450 |
$2,092
65,358
kWh
|
$1,151
-
kW-mo/yr
|
$197 | - | - | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $10,598 | $2,500 |
$7,147
223,329
kWh
|
$2,851
-
kW-mo/yr
|
$600 | - | - | - | |
05 | 2.4323: Use optimum size and capacity equipment | $30,735 | $8,017 |
$20,727
647,714
kWh
|
$8,268
-
kW-mo/yr
|
$1,740 | - | - | - | |
06 | 2.4131: Size electric motors for peak operating efficiency | $2,354 | $3,900 |
$1,523
49,531
kWh
|
$634
-
kW-mo/yr
|
$197 | - | - | - | |
07 | 2.2511: Insulate bare equipment | $7,967 | $8,398 | - | - | - |
$7,967
-
MMBtu
|
- | - | |
08 | 2.4133: Use most efficient type of electric motors | $38,797 | $151,526 |
$26,164
817,702
kWh
|
$10,454
-
kW-mo/yr
|
$2,179 | - | - | - | |
09 | 4.211: Consider use / purchase of bulk materials where possible | $52,500 | $45,000 | - | - | - | - |
$52,500
-
lb
|
- | |
10 | 3.5316: Contract a wood pallet recycling company | $1,800 | - | - | - | - | - |
$1,800
-
lb
|
- | |
TOTAL RECOMMENDED | $545,717 | $434,791 |
$57,653
1,803,634
kWh
|
$23,358
-
kW-mo/yr
|
$4,913 |
$374,749
-
MMBtu
|
$54,300
-
lb
|
$30,744 | ||
TOTAL IMPLEMENTED | $452,161 | $369,476 |
$35,403
1,106,389
kWh
|
$14,456
-
kW-mo/yr
|
$2,976 |
$366,782
-
MMBtu
|
$1,800
-
lb
|
$30,744 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs