ITAC Assessment: GT0666
ITAC logo
ITAC Assessment: GT0666
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Gypsum Wallboard
NAICS
n/a
SIC 3275: Gypsum Products
Sales Range $50
M
to 100
M
# of Employees 96
Plant Area 600,000
ft2
Annual Production 362,000
thousand feet
Production Hrs. Annual 8,272
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $548,479 19,430,833
kWh
Electricity Demand $286,545 32,562
kW-mo/yr
Electricity Fees $18,882 -
Natural Gas $2,576,743 824,797
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $545,717 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $452,161

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.8114: Change rate schedules or other changes in utility service $30,744 $35,000 - - - - - $30,744
02 2.1133: Adjust burners for efficient operation $366,782 $180,000 - - - $366,782
-
MMBtu
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,440 $450 $2,092
65,358
kWh
$1,151
-
kW-mo/yr
$197 - - -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $10,598 $2,500 $7,147
223,329
kWh
$2,851
-
kW-mo/yr
$600 - - -
05 2.4323: Use optimum size and capacity equipment $30,735 $8,017 $20,727
647,714
kWh
$8,268
-
kW-mo/yr
$1,740 - - -
06 2.4131: Size electric motors for peak operating efficiency $2,354 $3,900 $1,523
49,531
kWh
$634
-
kW-mo/yr
$197 - - -
07 2.2511: Insulate bare equipment $7,967 $8,398 - - - $7,967
-
MMBtu
- -
08 2.4133: Use most efficient type of electric motors $38,797 $151,526 $26,164
817,702
kWh
$10,454
-
kW-mo/yr
$2,179 - - -
09 4.211: Consider use / purchase of bulk materials where possible $52,500 $45,000 - - - - $52,500
-
lb
-
10 3.5316: Contract a wood pallet recycling company $1,800 - - - - - $1,800
-
lb
-
TOTAL RECOMMENDED $545,717 $434,791 $57,653
1,803,634
kWh
$23,358
-
kW-mo/yr
$4,913 $374,749
-
MMBtu
$54,300
-
lb
$30,744
TOTAL IMPLEMENTED $452,161 $369,476 $35,403
1,106,389
kWh
$14,456
-
kW-mo/yr
$2,976 $366,782
-
MMBtu
$1,800
-
lb
$30,744
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs