Assessment Year | 1999 |
---|---|
Principal Product | VHS Cassettes |
NAICS |
n/a
|
SIC | 3695: Magnetic And Optical Recording Media |
Sales Range | $50 M to 100M |
# of Employees | 170 |
Plant Area |
125,000
ft2
|
Annual Production | 74,600,000
pieces
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $433,461 | 8,044,842 |
kWh
|
$0.054 |
Electricity Fees | $30,342 | - |
|
- |
Natural Gas | $40,696 | 6,004 |
MMBtu
|
$6.78 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $63,069 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8113: Purchase gas directly from a contract gas supplier | $9,639 | - | - | - | - | - | $9,639 | |
02 | 2.8112: Combine utility meters | $1,117 | - | - | - | - | - | $1,117 | |
03 | 2.8112: Combine utility meters | $7,755 | - | - | - | - | - | $7,755 | |
04 | 3.4151: Minimize water usage | $113 | - | - | - | - | - | $113 | |
05 | 2.8112: Combine utility meters | $375 | - | - | - | - | - | $375 | |
06 | 3.4155: Meter waste water | $980 | $400 | - | - | - | - | $980 | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $19,035 | $5,000 |
$17,958
594,959
kWh
|
$1,077 | - | - | - | |
08 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $3,250 | $6,700 | - | - |
$3,250
-
lb
|
- | - | |
09 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $10,805 | $4,600 |
$10,193
337,632
kWh
|
$612 | - | - | - | |
10 | 4.441: Install automatic packing equipment | $10,000 | - | - | - | - | $10,000 | - | |
TOTAL RECOMMENDED | $63,069 | $16,700 |
$28,151
932,591
kWh
|
$1,689 |
$3,250
-
lb
|
$10,000 | $19,979 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs