Assessment Year | 1999 |
---|---|
Principal Product | Fluorescent Lighting |
NAICS |
n/a
|
SIC | 3645: Residential Electric Lighting Fixtures |
Sales Range | $100 M to 500M |
# of Employees | 400 |
Plant Area |
356,800
ft2
|
Annual Production | 10,000,000
pieces
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $264,438 | 4,130,715 |
kWh
|
$0.064 |
Natural Gas | $39,080 | 4,480 |
MMBtu
|
$8.72 |
LPG | $16,777 | 2,912 |
MMBtu
|
$5.76 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $918,264 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $891,108 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $20,275 | $4,960 |
$20,275
316,530
kWh
|
- | - | - | - | - | |
02 | 2.7132: Install timers on light switches in little used areas | $1,938 | $300 |
$1,938
30,188
kWh
|
- | - | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,740 | $750 |
$5,740
89,683
kWh
|
- | - | - | - | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $457 | $994 |
$457
7,034
kWh
|
- | - | - | - | - | |
05 | 3.5111: Filter and reuse hydraulic oil | $684 | $1,000 | - |
$187
-
lb
|
- | - | $497 | - | |
06 | 3.1192: Reduce scrap production | $215,560 | $112,500 | - | - | $(-11,000.0) | $226,560 | - | - | |
07 | 4.652: Replace existing equipment with more suitable substitutes | $673,610 | $245,000 | - | - | - | $23,610 | - | $650,000 | |
TOTAL RECOMMENDED | $918,264 | $365,504 |
$28,410
443,435
kWh
|
$187
-
lb
|
$(-11,000.0) | $250,170 | $497 | $650,000 | ||
TOTAL IMPLEMENTED | $891,108 | $357,800 |
$1,938
30,188
kWh
|
- | $(-11,000.0) | $250,170 | - | $650,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs