Assessment Year | 1998 |
---|---|
Principal Product | Steel Doors and Frames |
NAICS |
n/a
|
SIC | 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing |
Sales Range | $10 M to 50M |
# of Employees | 196 |
Plant Area |
171,000
ft2
|
Annual Production | 470,000
thousand feet
|
Production Hrs. Annual | 3,600
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $231,728 | 4,011,430 |
kWh
|
$0.058 |
Electricity Demand | $43,859 | 10,468 |
kW-mo/yr
|
$4.19 |
Electricity Fees | $24,144 | - |
|
- |
Natural Gas | $40,350 | 6,809 |
MMBtu
|
$5.93 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $43,815 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $26,743 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $5,800 | $5,000 | - |
$5,800
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $10,690 | $1,250 |
$5,131
99,062
kWh
|
$4,954
-
kW-mo/yr
|
$605 | - | - | - | - | |
03 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $1,582 | $3,116 |
$1,191
22,860
kWh
|
$301
-
kW-mo/yr
|
$90 | - | - | - | - | |
04 | 2.2437: Recover waste heat from equipment | $3,677 | $4,550 |
$(-53.0)
(-1,172)
kWh
|
- | - |
$3,730
-
MMBtu
|
- | - | - | |
05 | 3.4151: Minimize water usage | $6,576 | - | - | - | - | - |
$6,576
-
Tgal
|
- | - | |
06 | 3.2121: Convert to electrostatic powder coating | $7,580 | $4,800 | - | - | - | - | - |
$7,580
-
gal
|
- | |
07 | 3.2121: Convert to electrostatic powder coating | $4,410 | $5,400 | - | - | - | - | - |
$4,410
-
gal
|
- | |
08 | 4.431: Train operators for maximum operating efficiency | $3,500 | - | - | - | - | - | - | - | $3,500 | |
TOTAL RECOMMENDED | $43,815 | $24,116 |
$6,269
120,750
kWh
|
$11,055
-
kW-mo/yr
|
$695 |
$3,730
-
MMBtu
|
$6,576
-
Tgal
|
$11,990
-
gal
|
$3,500 | ||
TOTAL IMPLEMENTED | $26,743 | $10,800 |
$5,078
97,890
kWh
|
$10,754
-
kW-mo/yr
|
$605 |
$3,730
-
MMBtu
|
$6,576
-
Tgal
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs