| Assessment Year | 1998 |
|---|---|
| Principal Product | Spun Yarn / Filament |
| NAICS |
n/a
|
| SIC | 2281: Yarn Spinning Mills |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
400,000
ft2
|
| Annual Production | 13,000,000
lb
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $429,769 | 13,195,194 |
kWh
|
$0.033 |
| Electricity Demand | $240,365 | 27,660 |
kW-mo/yr
|
$8.69 |
| Electricity Fees | $50,616 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $111,528 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Fuel Oil #2 Savings | Administrative Changes Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8113: Purchase gas directly from a contract gas supplier | $25,720 | - | - | - | - | - |
$(-6,050.0)
-
MMBtu
|
$31,770 | - | |
| 02 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $6,647 | - | - | - | - |
$6,647
-
MMBtu
|
- | - | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,648 | - |
$4,082
125,440
kWh
|
$2,190
-
kW-mo/yr
|
$376 | - | - | - | - | |
| 04 | 3.4111: Use closed cycle process to minimize waste water production | $698 | $800 | - | - | - |
$685
-
MMBtu
|
- | - |
$13
-
Tgal
|
|
| 05 | 2.4239: Eliminate or reduce compressed air usage | $52,300 | $25,000 |
$15,243
468,054
kWh
|
$8,134
-
kW-mo/yr
|
$1,423 | - | - | $27,500 | - | |
| 06 | 2.4133: Use most efficient type of electric motors | $5,022 | $3,100 |
$3,090
94,959
kWh
|
$1,668
-
kW-mo/yr
|
$264 | - | - | - | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,493 | $66,930 |
$8,766
272,567
kWh
|
$4,693
-
kW-mo/yr
|
$1,034 | - | - | - | - | |
| TOTAL RECOMMENDED | $111,528 | $95,830 |
$31,181
961,020
kWh
|
$16,685
-
kW-mo/yr
|
$3,097 |
$7,332
-
MMBtu
|
$(-6,050.0)
-
MMBtu
|
$59,270 |
$13
-
Tgal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Fuel Oil #2 Savings | Administrative Changes Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs