| Assessment Year | 1998 |
|---|---|
| Principal Product | Stamped Metal Products |
| NAICS |
n/a
|
| SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 65 |
| Plant Area |
30,000
ft2
|
| Annual Production | 1,200,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $24,486 | 699,590 |
kWh
|
$0.035 |
| Electricity Demand | $23,391 | 2,034 |
kW-mo/yr
|
$11.50 |
| Electricity Fees | $8,339 | - |
|
- |
| Natural Gas | $2,325 | 315 |
MMBtu
|
$7.38 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $5,504 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,954 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,309 | $3,080 |
$694
19,930
kWh
|
$615
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $645 | $2,200 |
$445
12,603
kWh
|
$200
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7245: Use direct air supply to exhaust hoods | $860 | $4,625 | - | - |
$860
-
MMBtu
|
- | - | |
| 04 | 2.7243: Improve air circulation with destratification fans / other methods | $430 | $1,992 | - | - |
$430
-
MMBtu
|
- | - | |
| 05 | 4.441: Install automatic packing equipment | $2,260 | $3,125 | - | - | - |
$770
-
lb
|
$1,490 | |
| TOTAL RECOMMENDED | $5,504 | $15,022 |
$1,139
32,533
kWh
|
$815
-
kW-mo/yr
|
$1,290
-
MMBtu
|
$770
-
lb
|
$1,490 | ||
| TOTAL IMPLEMENTED | $1,954 | $5,280 |
$1,139
32,533
kWh
|
$815
-
kW-mo/yr
|
- | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs