Assessment Year | 1998 |
---|---|
Principal Product | Scrap Processing Equipment |
NAICS |
n/a
|
SIC | 3569: General Industrial Machinery and Equipment, Not Elsewhere |
Sales Range | $10 M to 50M |
# of Employees | 210 |
Plant Area |
150,000
ft2
|
Annual Production | 9,000
ton
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $132,327 | 6,134,525 |
kWh
|
$0.022 |
Electricity Demand | $152,685 | 18,785 |
kW-mo/yr
|
$8.13 |
Electricity Fees | $54,288 | - |
|
- |
Natural Gas | $129,861 | 17,379 |
MMBtu
|
$7.47 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $65,773 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,230 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7124: Make a practice of turning off lights when not needed | $303 | - |
$153
7,034
kWh
|
$136
-
kW-mo/yr
|
$14 | - | - | |
02 | 2.2514: Cover open tanks | $6,346 | $1,838 |
$2,869
131,594
kWh
|
$3,062
-
kW-mo/yr
|
$415 | - | - | |
03 | 2.6218: Turn off equipment when not in use | $6,251 | - |
$2,668
122,509
kWh
|
$3,165
-
kW-mo/yr
|
$418 | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,049 | $5,558 |
$692
31,653
kWh
|
$1,182
-
kW-mo/yr
|
$175 | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,160 | $750 |
$1,594
72,978
kWh
|
$1,359
-
kW-mo/yr
|
$207 | - | - | |
06 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $12,300 | $2,000 | - | - | - | - | $12,300 | |
07 | 3.5146: Utilize a central coolant system for cleaning and reuse of metal working fluid | $21,400 | $32,860 | - | - | - | - | $21,400 | |
08 | 3.5111: Filter and reuse hydraulic oil | $7,448 | $4,500 | - | - | - | - | $7,448 | |
09 | 4.512: Condense operation into one building | $6,516 | - | - | - | - | $6,516 | - | |
TOTAL RECOMMENDED | $65,773 | $47,506 |
$7,976
365,768
kWh
|
$8,904
-
kW-mo/yr
|
$1,229 | $6,516 | $41,148 | ||
TOTAL IMPLEMENTED | $16,230 | $750 |
$4,415
202,521
kWh
|
$4,660
-
kW-mo/yr
|
$639 | $6,516 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs