ITAC Assessment: GT0641
ITAC logo
ITAC Assessment: GT0641
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Manufactured Housing
NAICS
n/a
SIC 2451: Mobile Homes
Sales Range $50
M
to 100
M
# of Employees 250
Plant Area 121,802
ft2
Annual Production 3,030
pieces
Production Hrs. Annual 2,020
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $54,819 1,011,430
kWh
Electricity Demand $30,841 4,021
kW-mo/yr
Electricity Fees $9,661 -
Natural Gas $17,124 2,379
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $91,924 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $28,834

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings
01 3.5311: Recover and reuse waste material $60,000 $60,000 - - - $60,000
-
lb
02 2.4314: Use synthetic lubricant $1,162 - $661
12,309
kWh
$501
-
kW-mo/yr
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,947 $5,062 $1,503
29,601
kWh
$1,304
-
kW-mo/yr
$140 -
04 3.1172: Revise raw material specs $14,100 - - - - $14,100
-
lb
05 3.5311: Recover and reuse waste material $2,640 - - - - $2,640
-
lb
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,932 $2,700 $5,932
109,320
kWh
$4,479
-
kW-mo/yr
$521 -
07 3.1162: Use less wasteful packaging $143 - - - - $143
-
lb
TOTAL RECOMMENDED $91,924 $67,762 $8,096
151,230
kWh
$6,284
-
kW-mo/yr
$661 $76,883
-
lb
TOTAL IMPLEMENTED $28,834 $2,700 $6,593
121,629
kWh
$4,980
-
kW-mo/yr
$521 $16,740
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs