ITAC Assessment: GT0626
ITAC logo
ITAC Assessment: GT0626
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Finished Carpet
NAICS
n/a
SIC 2273: Carpets and Rugs
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 184,680
ft2
Annual Production 45,000,000
thousand feet
Production Hrs. Annual 2,500
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $67,117 2,314,478
kWh
Electricity Demand $26,860 8,792
kW-mo/yr
Electricity Fees $4,362 -
Natural Gas $190,793 44,745
MMBtu
LPG $36,068 5,152
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $59,187 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $50,992

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings Increase in Production Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,741 $950 $1,734
59,789
kWh
$876
-
kW-mo/yr
$131 - - - - - -
02 2.8114: Change rate schedules or other changes in utility service $21,185 - - - - - - - - $21,185 -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,580 $11,230 $1,000
34,584
kWh
$505
-
kW-mo/yr
$75 - - - - - -
04 3.4114: Replace city water with recycled water via cooling tower $2,730 $1,420 - - - - $2,730
-
Tgal
- - - -
05 2.2136: Install / repair insulation on steam lines $400 $620 - - - $400
-
MMBtu
- - - - -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,570 $7,580 $1,627
55,979
kWh
$821
-
kW-mo/yr
$122 - - - - - -
07 4.611: Begin a practice of predictive / preventative maintenance $26,666 $4,200 $241
8,206
kWh
$121
-
kW-mo/yr
- - - - $704 - $25,600
08 3.1175: Use a different or recycled raw material $1,315 $438 - - - - - $1,315
-
lb
- - -
TOTAL RECOMMENDED $59,187 $26,438 $4,602
158,558
kWh
$2,323
-
kW-mo/yr
$328 $400
-
MMBtu
$2,730
-
Tgal
$1,315
-
lb
$704 $21,185 $25,600
TOTAL IMPLEMENTED $50,992 $5,770 $1,975
67,995
kWh
$997
-
kW-mo/yr
$131 $400
-
MMBtu
- - $704 $21,185 $25,600
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs