| Assessment Year | 1997 |
|---|---|
| Principal Product | Finished Carpet |
| NAICS |
n/a
|
| SIC | 2273: Carpets and Rugs |
| Sales Range | $10 M to 50M |
| # of Employees | 120 |
| Plant Area |
184,680
ft2
|
| Annual Production | 45,000,000
thousand feet
|
| Production Hrs. Annual | 2,500
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $67,117 | 2,314,478 |
kWh
|
$0.029 |
| Electricity Demand | $26,860 | 8,792 |
kW-mo/yr
|
$3.06 |
| Electricity Fees | $4,362 | - |
|
- |
| Natural Gas | $190,793 | 44,745 |
MMBtu
|
$4.26 |
| LPG | $36,068 | 5,152 |
MMBtu
|
$7.00 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $59,187 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $50,992 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,741 | $950 |
$1,734
59,789
kWh
|
$876
-
kW-mo/yr
|
$131 | - | - | - | - | - | - | |
| 02 | 2.8114: Change rate schedules or other changes in utility service | $21,185 | - | - | - | - | - | - | - | - | $21,185 | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,580 | $11,230 |
$1,000
34,584
kWh
|
$505
-
kW-mo/yr
|
$75 | - | - | - | - | - | - | |
| 04 | 3.4114: Replace city water with recycled water via cooling tower | $2,730 | $1,420 | - | - | - | - |
$2,730
-
Tgal
|
- | - | - | - | |
| 05 | 2.2136: Install / repair insulation on steam lines | $400 | $620 | - | - | - |
$400
-
MMBtu
|
- | - | - | - | - | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,570 | $7,580 |
$1,627
55,979
kWh
|
$821
-
kW-mo/yr
|
$122 | - | - | - | - | - | - | |
| 07 | 4.611: Begin a practice of predictive / preventative maintenance | $26,666 | $4,200 |
$241
8,206
kWh
|
$121
-
kW-mo/yr
|
- | - | - | - | $704 | - | $25,600 | |
| 08 | 3.1175: Use a different or recycled raw material | $1,315 | $438 | - | - | - | - | - |
$1,315
-
lb
|
- | - | - | |
| TOTAL RECOMMENDED | $59,187 | $26,438 |
$4,602
158,558
kWh
|
$2,323
-
kW-mo/yr
|
$328 |
$400
-
MMBtu
|
$2,730
-
Tgal
|
$1,315
-
lb
|
$704 | $21,185 | $25,600 | ||
| TOTAL IMPLEMENTED | $50,992 | $5,770 |
$1,975
67,995
kWh
|
$997
-
kW-mo/yr
|
$131 |
$400
-
MMBtu
|
- | - | $704 | $21,185 | $25,600 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs