Assessment Year | 1997 |
---|---|
Principal Product | Packaged Sausage |
NAICS |
n/a
|
SIC | 2013: Sausages and Other Prepared Meat Products |
Sales Range | $5 M to 10M |
# of Employees | 50 |
Plant Area |
27,000
ft2
|
Annual Production | 5,000,000
lb
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $30,452 | 1,175,850 |
kWh
|
$0.026 |
Electricity Demand | $29,544 | 2,603 |
kW-mo/yr
|
$11.35 |
Electricity Fees | $3,046 | - |
|
- |
Natural Gas | $27,533 | 4,648 |
MMBtu
|
$5.92 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,975 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,325 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7243: Improve air circulation with destratification fans / other methods | $1,454 | $1,200 |
$855
33,118
kWh
|
$518
-
kW-mo/yr
|
$81 | - | - | - | |
02 | 2.2136: Install / repair insulation on steam lines | $1,260 | $1,870 | - | - | - |
$1,260
-
MMBtu
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,270 | $6,830 |
$2,963
114,302
kWh
|
$2,002
-
kW-mo/yr
|
$305 | - | - | - | |
04 | 2.2515: Use optimum thickness insulation | $390 | $900 |
$228
8,792
kWh
|
$136
-
kW-mo/yr
|
$26 | - | - | - | |
05 | 3.4154: Eliminate leaks in water lines and valves | $55 | $50 | - | - | - |
$30
-
MMBtu
|
- |
$25
-
Tgal
|
|
06 | 4.112: Replace old machine with new automatic multi-station tool | $9,546 | $50,000 | - | - | - |
$1,954
-
MMBtu
|
$7,500 |
$92
-
Tgal
|
|
TOTAL RECOMMENDED | $17,975 | $60,850 |
$4,046
156,212
kWh
|
$2,656
-
kW-mo/yr
|
$412 |
$3,244
-
MMBtu
|
$7,500 |
$117
-
Tgal
|
||
TOTAL IMPLEMENTED | $5,325 | $6,880 |
$2,963
114,302
kWh
|
$2,002
-
kW-mo/yr
|
$305 |
$30
-
MMBtu
|
- |
$25
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs