ITAC Assessment: GT0618
ITAC logo
ITAC Assessment: GT0618
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product dried egg product
NAICS
n/a
SIC 2015: Poultry Slaughtering and Processing
Sales Range $100
M
to 500
M
# of Employees 65
Plant Area 47,000
ft2
Annual Production 30,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $172,412 6,140,387
kWh
Electricity Demand $72,096 6,000
kW-mo/yr
Electricity Fees $15,607 -
Natural Gas $1,304,714 247,896
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $671,484 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $216,334

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings LPG Savings Water Disposal Savings Administrative Changes Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $52,000 $2,000 - - $52,000
-
MMBtu
- - -
02 2.1224: Replace boiler $57,000 $100,000 - - $57,000
-
MMBtu
- - -
03 2.2511: Insulate bare equipment $3,600 $3,000 - - $3,600
-
MMBtu
- - -
04 2.8113: Purchase gas directly from a contract gas supplier $149,009 $238,000 - - - $(-55,228.0)
-
MMBtu
- $204,237
05 3.4151: Minimize water usage $3,550 $3,450 - - $3,090
-
MMBtu
- $460
-
Tgal
-
06 2.4133: Use most efficient type of electric motors $8,175 $99,710 $7,712
335,287
kWh
$463 - - - -
07 3.4151: Minimize water usage $398,150 $400,000 - - $385,900
-
MMBtu
- $12,250
-
Tgal
-
TOTAL RECOMMENDED $671,484 $846,160 $7,712
335,287
kWh
$463 $501,590
-
MMBtu
$(-55,228.0)
-
MMBtu
$12,710
-
Tgal
$204,237
TOTAL IMPLEMENTED $216,334 $346,160 $7,712
335,287
kWh
$463 $58,690
-
MMBtu
$(-55,228.0)
-
MMBtu
$460
-
Tgal
$204,237
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Natural Gas Savings LPG Savings Water Disposal Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs