| Assessment Year | 1997 |
|---|---|
| Principal Product | dried egg product |
| NAICS |
n/a
|
| SIC | 2015: Poultry Slaughtering and Processing |
| Sales Range | $100 M to 500M |
| # of Employees | 65 |
| Plant Area |
47,000
ft2
|
| Annual Production | 30,000,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $172,412 | 6,140,387 |
kWh
|
$0.028 |
| Electricity Demand | $72,096 | 6,000 |
kW-mo/yr
|
$12.02 |
| Electricity Fees | $15,607 | - |
|
- |
| Natural Gas | $1,304,714 | 247,896 |
MMBtu
|
$5.26 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $671,484 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $216,334 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | LPG Savings | Water Disposal Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $52,000 | $2,000 | - | - |
$52,000
-
MMBtu
|
- | - | - | |
| 02 | 2.1224: Replace boiler | $57,000 | $100,000 | - | - |
$57,000
-
MMBtu
|
- | - | - | |
| 03 | 2.2511: Insulate bare equipment | $3,600 | $3,000 | - | - |
$3,600
-
MMBtu
|
- | - | - | |
| 04 | 2.8113: Purchase gas directly from a contract gas supplier | $149,009 | $238,000 | - | - | - |
$(-55,228.0)
-
MMBtu
|
- | $204,237 | |
| 05 | 3.4151: Minimize water usage | $3,550 | $3,450 | - | - |
$3,090
-
MMBtu
|
- |
$460
-
Tgal
|
- | |
| 06 | 2.4133: Use most efficient type of electric motors | $8,175 | $99,710 |
$7,712
335,287
kWh
|
$463 | - | - | - | - | |
| 07 | 3.4151: Minimize water usage | $398,150 | $400,000 | - | - |
$385,900
-
MMBtu
|
- |
$12,250
-
Tgal
|
- | |
| TOTAL RECOMMENDED | $671,484 | $846,160 |
$7,712
335,287
kWh
|
$463 |
$501,590
-
MMBtu
|
$(-55,228.0)
-
MMBtu
|
$12,710
-
Tgal
|
$204,237 | ||
| TOTAL IMPLEMENTED | $216,334 | $346,160 |
$7,712
335,287
kWh
|
$463 |
$58,690
-
MMBtu
|
$(-55,228.0)
-
MMBtu
|
$460
-
Tgal
|
$204,237 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | LPG Savings | Water Disposal Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs