Assessment Year | 1997 |
---|---|
Principal Product | Rugs |
NAICS |
n/a
|
SIC | 2147: |
Sales Range | $50 M to 100M |
# of Employees | 500 |
Plant Area |
410,000
ft2
|
Annual Production | 14,600,000
pieces
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $262,735 | 8,628,371 |
kWh
|
$0.030 |
Electricity Demand | $163,145 | 17,887 |
kW-mo/yr
|
$9.12 |
Electricity Fees | $17,034 | - |
|
- |
Natural Gas | $705,955 | 196,281 |
MMBtu
|
$3.60 |
LPG | $39,174 | 5,771 |
MMBtu
|
$6.79 |
Fuel Oil #6 | $31,311 | 9,031 |
MMBtu
|
$3.47 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $421,577 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $123,367 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $42,000 | $64,500 | - | - | - |
$42,000
-
MMBtu
|
- | - | - | - | - | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $11,020 | $24,000 | - | - | - |
$11,020
-
MMBtu
|
- | - | - | - | - | |
03 | 2.2424: Use heat in flue gases to preheat products or materials | $11,000 | $30,000 | - | - | - |
$11,000
-
MMBtu
|
- | - | - | - | - | |
04 | 4.652: Replace existing equipment with more suitable substitutes | $278,260 | - | - | - | - |
$6,260
-
MMBtu
|
- | - | - | - | $272,000 | |
05 | 3.4111: Use closed cycle process to minimize waste water production | $70,347 | $112,950 | - | - | - |
$55,190
-
MMBtu
|
$9,154
-
Tgal
|
- | $650 |
$5,353
-
Tgal
|
- | |
06 | 2.6218: Turn off equipment when not in use | $5,355 | $4,400 |
$3,409
111,958
kWh
|
$1,738
-
kW-mo/yr
|
$208 | - | - | - | - | - | - | |
07 | 3.4155: Meter waste water | $890 | $1,800 | - | - | - | - | - | $890 | - | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,705 | $3,890 |
$998
32,532
kWh
|
$1,707
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
TOTAL RECOMMENDED | $421,577 | $241,540 |
$4,407
144,490
kWh
|
$3,445
-
kW-mo/yr
|
$208 |
$125,470
-
MMBtu
|
$9,154
-
Tgal
|
$890 | $650 |
$5,353
-
Tgal
|
$272,000 | ||
TOTAL IMPLEMENTED | $123,367 | $201,450 | - | - | - |
$108,210
-
MMBtu
|
$9,154
-
Tgal
|
- | $650 |
$5,353
-
Tgal
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs