ITAC Assessment: GT0608
ITAC logo
ITAC Assessment: GT0608
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Aggregate Stone
NAICS
n/a
SIC 3281: Cut Stone and Stone Products
Sales Range $10
M
to 50
M
# of Employees 66
Plant Area
n/a
Annual Production 1,800,000
ton
Production Hrs. Annual 3,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $156,563 3,914,127
kWh
Electricity Demand $221,919 20,065
kW-mo/yr
Electricity Fees $22,709 -
LPG $2,500 192
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $39,293 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $27,600

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings LPG Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.8112: Combine utility meters $8,120 $18,860 - - - - $8,120 -
02 2.4133: Use most efficient type of electric motors $426 $6,227 $196
4,982
kWh
$206
-
kW-mo/yr
$24 - - -
03 2.6218: Turn off equipment when not in use $5,260 $4,000 $2,417
60,375
kWh
$2,545
-
kW-mo/yr
$298 - - -
04 2.6218: Turn off equipment when not in use $7,317 $3,510 $3,357
83,822
kWh
$3,546
-
kW-mo/yr
$414 - - -
05 3.5112: Reprocess spent oils on site for re-use $2,625 $3,500 - - - - - $2,625
06 2.5124: Use gravity feeds wherever possible $3,425 $5,130 $1,572
39,273
kWh
$1,659
-
kW-mo/yr
$194 - - -
07 2.5124: Use gravity feeds wherever possible $2,568 $14,250 $1,182
29,308
kWh
$1,241
-
kW-mo/yr
$145 - - -
08 2.7122: Disconnect ballasts $552 $84 $253
6,448
kWh
$266
-
kW-mo/yr
$33 - - -
09 3.7311: Maintain machines to reduce leaks $6,500 $5,000 - - - - - $6,500
10 3.5112: Reprocess spent oils on site for re-use $2,500 $9,400 - - - $2,500
-
MMBtu
- -
TOTAL RECOMMENDED $39,293 $69,961 $8,977
224,208
kWh
$9,463
-
kW-mo/yr
$1,108 $2,500
-
MMBtu
$8,120 $9,125
TOTAL IMPLEMENTED $27,600 $47,211 $7,795
194,900
kWh
$8,222
-
kW-mo/yr
$963 $2,500
-
MMBtu
$8,120 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings LPG Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs