Assessment Year | 1996 |
---|---|
Principal Product | Billboards |
NAICS |
n/a
|
SIC | 3317: Steel Pipe and Tubes |
Sales Range | $10 M to 50M |
# of Employees | 18 |
Plant Area |
50,000
ft2
|
Annual Production | 1,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $31,558 | 390,094 |
kWh
|
$0.081 |
Electricity Demand | $17,099 | 1,231 |
kW-mo/yr
|
$13.89 |
Electricity Fees | $4,027 | - |
|
- |
Natural Gas | $3,887 | 669 |
MMBtu
|
$5.81 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $25,864 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,444 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $4,940 | - | - | - | $4,940 | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $720 | $300 | - |
$720
-
kW-mo/yr
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,504 | $11,400 |
$3,784
103,751
kWh
|
$1,720
-
kW-mo/yr
|
- | |
04 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $14,700 | $5,000 | - | - | $14,700 | |
TOTAL RECOMMENDED | $25,864 | $16,700 |
$3,784
103,751
kWh
|
$2,440
-
kW-mo/yr
|
$19,640 | ||
TOTAL IMPLEMENTED | $10,444 | $11,400 |
$3,784
103,751
kWh
|
$1,720
-
kW-mo/yr
|
$4,940 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs