Assessment Year | 1996 |
---|---|
Principal Product | Displays and Signs |
NAICS |
n/a
|
SIC | 3993: Signs and Advertising Specialties |
Sales Range | $1 M to 5M |
# of Employees | 175 |
Plant Area |
115,700
ft2
|
Annual Production | 1,000,000
lb
|
Production Hrs. Annual | 2,550
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $169,654 | 2,337,925 |
kWh
|
$0.073 |
Electricity Demand | $36,514 | 10,708 |
kW-mo/yr
|
$3.41 |
Electricity Fees | $15,378 | - |
|
- |
Natural Gas | $50,003 | 6,505 |
MMBtu
|
$7.69 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $57,489 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $22,219 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $5,660 | $18,860 | - | - | - | - | $5,660 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,459 | $2,640 |
$5,135
65,944
kWh
|
$1,929
-
kW-mo/yr
|
$395 | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,100 | $600 |
$6,848
86,753
kWh
|
$1,718
-
kW-mo/yr
|
$534 | - | - | |
04 | 2.6218: Turn off equipment when not in use | $33,280 | $30,000 |
$22,736
287,808
kWh
|
$8,653
-
kW-mo/yr
|
$1,891 | - | - | |
05 | 3.4155: Meter waste water | $500 | $600 | - | - | - | - | $500 | |
06 | 3.4151: Minimize water usage | $1,490 | $3,000 | - | - | - |
$1,490
-
Tgal
|
- | |
TOTAL RECOMMENDED | $57,489 | $55,700 |
$34,719
440,505
kWh
|
$12,300
-
kW-mo/yr
|
$2,820 |
$1,490
-
Tgal
|
$6,160 | ||
TOTAL IMPLEMENTED | $22,219 | $22,100 |
$11,983
152,697
kWh
|
$3,647
-
kW-mo/yr
|
$929 | - | $5,660 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs