ITAC Assessment: GT0596
ITAC logo
ITAC Assessment: GT0596
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Polystyrene
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 100
Plant Area 65,000
ft2
Annual Production 3,000,000
lb
Production Hrs. Annual 5,100
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $28,029 785,170
kWh
Electricity Demand $36,613 2,800
kW-mo/yr
Electricity Fees $3,232 -
Natural Gas $102,170 30,525
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $101,546 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $37,810

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.8112: Combine utility meters $3,080 $5,000 - - - - $3,080 -
02 2.8113: Purchase gas directly from a contract gas supplier $19,400 - - - - - $19,400 -
03 2.2414: Use waste heat from hot flue gases to preheat $17,000 $41,250 - - - $17,000
-
MMBtu
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,410 $200 $647
23,740
kWh
$704
-
kW-mo/yr
$59 - - -
05 3.1162: Use less wasteful packaging $58,140 $38,250 - - - - - $58,140
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,576 $3,850 $334
12,309
kWh
$1,168
-
kW-mo/yr
$74 - - -
07 2.4133: Use most efficient type of electric motors $940 $5,130 $430
15,826
kWh
$464
-
kW-mo/yr
$46 - - -
TOTAL RECOMMENDED $101,546 $93,680 $1,411
51,875
kWh
$2,336
-
kW-mo/yr
$179 $17,000
-
MMBtu
$22,480 $58,140
TOTAL IMPLEMENTED $37,810 $41,450 $647
23,740
kWh
$704
-
kW-mo/yr
$59 $17,000
-
MMBtu
$19,400 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs