| Assessment Year | 1996 |
|---|---|
| Principal Product | Polystyrene |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 100 |
| Plant Area |
65,000
ft2
|
| Annual Production | 3,000,000
lb
|
| Production Hrs. Annual | 5,100
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $28,029 | 785,170 |
kWh
|
$0.036 |
| Electricity Demand | $36,613 | 2,800 |
kW-mo/yr
|
$13.08 |
| Electricity Fees | $3,232 | - |
|
- |
| Natural Gas | $102,170 | 30,525 |
MMBtu
|
$3.35 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $101,546 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $37,810 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8112: Combine utility meters | $3,080 | $5,000 | - | - | - | - | $3,080 | - | |
| 02 | 2.8113: Purchase gas directly from a contract gas supplier | $19,400 | - | - | - | - | - | $19,400 | - | |
| 03 | 2.2414: Use waste heat from hot flue gases to preheat | $17,000 | $41,250 | - | - | - |
$17,000
-
MMBtu
|
- | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,410 | $200 |
$647
23,740
kWh
|
$704
-
kW-mo/yr
|
$59 | - | - | - | |
| 05 | 3.1162: Use less wasteful packaging | $58,140 | $38,250 | - | - | - | - | - | $58,140 | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,576 | $3,850 |
$334
12,309
kWh
|
$1,168
-
kW-mo/yr
|
$74 | - | - | - | |
| 07 | 2.4133: Use most efficient type of electric motors | $940 | $5,130 |
$430
15,826
kWh
|
$464
-
kW-mo/yr
|
$46 | - | - | - | |
| TOTAL RECOMMENDED | $101,546 | $93,680 |
$1,411
51,875
kWh
|
$2,336
-
kW-mo/yr
|
$179 |
$17,000
-
MMBtu
|
$22,480 | $58,140 | ||
| TOTAL IMPLEMENTED | $37,810 | $41,450 |
$647
23,740
kWh
|
$704
-
kW-mo/yr
|
$59 |
$17,000
-
MMBtu
|
$19,400 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs