Assessment Year | 1996 |
---|---|
Principal Product | Nylon Yarn |
NAICS |
n/a
|
SIC | 2281: Yarn Spinning Mills |
Sales Range | $50 M to 100M |
# of Employees | 650 |
Plant Area |
318,740
ft2
|
Annual Production | 60,000,000
lb
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,277,028 | 50,475,382 |
kWh
|
$0.025 |
Electricity Demand | $947,485 | 88,799 |
kW-mo/yr
|
$10.67 |
Electricity Fees | $153,106 | - |
|
- |
Natural Gas | $432,627 | 124,622 |
MMBtu
|
$3.47 |
Fuel Oil #2 | $78,545 | 18,182 |
MMBtu
|
$4.32 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $79,723 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $38,120 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $26,920 | $147,550 |
$16,640
657,679
kWh
|
$10,030
-
kW-mo/yr
|
$250 | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $13,303 | $11,440 |
$8,297
327,960
kWh
|
$5,006
-
kW-mo/yr
|
- | - | |
03 | 2.4314: Use synthetic lubricant | $1,900 | - |
$1,186
46,893
kWh
|
$674
-
kW-mo/yr
|
$40 | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,670 | $1,000 |
$3,540
140,094
kWh
|
$2,130
-
kW-mo/yr
|
- | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $28,300 | $55,000 |
$28,300
1,119,285
kWh
|
- | - | - | |
06 | 3.4155: Meter waste water | $3,630 | - | - | - | - |
$3,630
-
Tgal
|
|
TOTAL RECOMMENDED | $79,723 | $214,990 |
$57,963
2,291,911
kWh
|
$17,840
-
kW-mo/yr
|
$290 |
$3,630
-
Tgal
|
||
TOTAL IMPLEMENTED | $38,120 | $148,550 |
$21,366
844,666
kWh
|
$12,834
-
kW-mo/yr
|
$290 |
$3,630
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs