ITAC Assessment: GT0591
ITAC logo
ITAC Assessment: GT0591
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product finished cloth
NAICS
n/a
SIC 2322: Men's and Boys' Underwear and Nightwear
Sales Range $5
M
to 10
M
# of Employees 30
Plant Area 30,000
ft2
Annual Production 28,200,000
lb
Production Hrs. Annual 8,200
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $274,459 5,670,575
kWh
Electricity Demand $44,100 12,600
kW-mo/yr
Electricity Fees $26,066 -
Natural Gas $463,686 146,531
MMBtu
Fuel Oil #2 $4,930 1,609
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $93,520 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,440

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $4,220 $3,800 - - - $4,220
-
MMBtu
- - -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $18,290 $15,000 $15,143
341,442
kWh
$1,764
-
kW-mo/yr
$1,383 - - - -
03 2.2121: Increase amount of condensate returned $21,690 $11,410 - - - - $11,990
-
Tgal
- $9,700
-
Tgal
04 2.2514: Cover open tanks $2,320 $1,200 - - - $2,320
-
MMBtu
- - -
05 3.4154: Eliminate leaks in water lines and valves $5,120 $200 - - - $2,130
-
MMBtu
$1,645
-
Tgal
- $1,345
-
Tgal
06 2.2113: Repair or replace steam traps $7,900 $800 - - - $7,900
-
MMBtu
- - -
07 3.4155: Meter waste water $17,050 $1,800 - - - - - $17,050 -
08 2.4133: Use most efficient type of electric motors $6,900 $50,750 $6,014
124,267
kWh
$546
-
kW-mo/yr
$340 - - - -
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,520 $1,020 $1,319
27,257
kWh
$126
-
kW-mo/yr
$75 - - - -
10 2.3212: Optimize plant power factor $8,510 $13,400 - $8,510
-
kW-mo/yr
- - - - -
TOTAL RECOMMENDED $93,520 $99,380 $22,476
492,966
kWh
$10,946
-
kW-mo/yr
$1,798 $16,570
-
MMBtu
$13,635
-
Tgal
$17,050 $11,045
-
Tgal
TOTAL IMPLEMENTED $7,440 $1,400 - - - $4,450
-
MMBtu
$1,645
-
Tgal
- $1,345
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs