ITAC Assessment: GT0583
ITAC logo
ITAC Assessment: GT0583
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Apparel
NAICS
n/a
SIC 2322: Men's and Boys' Underwear and Nightwear
Sales Range $10
M
to 50
M
# of Employees 280
Plant Area 163,200
ft2
Annual Production 1,300,000
pieces
Production Hrs. Annual 2,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $112,864 2,531,946
kWh
Electricity Demand $87,789 11,352
kW-mo/yr
Electricity Fees $10,033 -
Natural Gas $2,024 256
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $33,830 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $33,630

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings
01 2.8112: Combine utility meters $9,200 $18,400 - - $9,200 -
02 2.7229: Air condition only space necessary $17,420 $15,000 $12,515
345,545
kWh
$4,075
-
kW-mo/yr
$830 -
03 2.4133: Use most efficient type of electric motors $90 $3,900 $44
879
kWh
$42
-
kW-mo/yr
$4 -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $200 $360 $144
2,052
kWh
$46
-
kW-mo/yr
$10 -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $390 $500 $201
3,810
kWh
$170
-
kW-mo/yr
$19 -
06 2.7124: Make a practice of turning off lights when not needed $390 - $270
7,034
kWh
$101
-
kW-mo/yr
$19 -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $1,860 $3,000 $666
12,016
kWh
$534
-
kW-mo/yr
$60 $600
-
lb
08 3.5217: Reuse / recycle/ sell paper products $4,280 $7,050 - - - $4,280
-
lb
TOTAL RECOMMENDED $33,830 $48,210 $13,840
371,336
kWh
$4,968
-
kW-mo/yr
$10,142 $4,880
-
lb
TOTAL IMPLEMENTED $33,630 $47,850 $13,696
369,284
kWh
$4,922
-
kW-mo/yr
$10,132 $4,880
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs