Assessment Year | 1995 |
---|---|
Principal Product | Conduit Seal |
NAICS |
n/a
|
SIC | 3568: Mechanical Power Transmission Equipment, Not Elsewhere Classified |
Sales Range | $500 k to 1M |
# of Employees | 7 |
Plant Area |
30,000
ft2
|
Annual Production | 1,000,000
lb
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $50,993 | 454,279 |
kWh
|
$0.11 |
Natural Gas | $731 | 120 |
MMBtu
|
$6.09 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $31,575 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,350 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $6,700 | - |
$6,700
-
kWh
|
- | |
02 | 2.2437: Recover waste heat from equipment | $670 | $1,450 |
$670
35,170
kWh
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $510 | $720 |
$510
4,689
kWh
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,840 | $200 |
$2,840
25,205
kWh
|
- | |
05 | 3.1191: Change procedures / equipment / operating conditions | $20,855 | $66,000 |
$5,205
46,600
kWh
|
$15,650
-
lb
|
|
TOTAL RECOMMENDED | $31,575 | $68,370 |
$15,925
111,664
kWh
|
$15,650
-
lb
|
||
TOTAL IMPLEMENTED | $3,350 | $920 |
$3,350
29,894
kWh
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs