ITAC Assessment: GT0566
ITAC logo
ITAC Assessment: GT0566
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Bottled Soft Drinks
NAICS
n/a
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $50
M
to 100
M
# of Employees 116
Plant Area 200,000
ft2
Annual Production 1,152,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $641,429 12,391,266
kWh
Natural Gas $154,843 51,844
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $102,598 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $89,538

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings
01 2.4133: Use most efficient type of electric motors $3,780 $35,550 $3,780
71,805
kWh
- -
02 2.2221: Use immersion heating in tanks, melting pots, etc $81,900 $80,000 - $81,900
-
MMBtu
-
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $795 $1,170 $795
14,947
kWh
- -
04 2.2621: Modify refrigeration system to operate at a lower pressure $10,700 - $10,700
468,933
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $2,360 $6,048 $2,360
52,755
kWh
- -
06 2.7144: Install spectral reflectors / delamp $2,940 $3,560 $2,940
65,358
kWh
- -
07 3.4151: Minimize water usage $123 $324 - - $123
-
Tgal
TOTAL RECOMMENDED $102,598 $126,652 $20,575
673,798
kWh
$81,900
-
MMBtu
$123
-
Tgal
TOTAL IMPLEMENTED $89,538 $120,604 $7,515
152,110
kWh
$81,900
-
MMBtu
$123
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs