| Assessment Year | 1995 |
|---|---|
| Principal Product | Lead-Acid Batteries |
| NAICS |
n/a
|
| SIC | 3692: Primary Batteries, Dry and Wet |
| Sales Range | $10 M to 50M |
| # of Employees | 118 |
| Plant Area |
108,000
ft2
|
| Annual Production | 743,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $364,846 | 8,739,156 |
kWh
|
$0.042 |
| Natural Gas | $106,416 | 18,218 |
MMBtu
|
$5.84 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $39,940 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,420 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,590 | $23,400 |
$2,590
107,855
kWh
|
- | - | |
| 02 | 2.7144: Install spectral reflectors / delamp | $910 | - |
$910
37,808
kWh
|
- | - | |
| 03 | 2.4133: Use most efficient type of electric motors | $2,320 | $58,400 |
$2,320
96,717
kWh
|
- | - | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,600 | $2,270 |
$2,600
109,320
kWh
|
- | - | |
| 05 | 2.2414: Use waste heat from hot flue gases to preheat | $13,120 | $13,340 | - |
$13,120
-
MMBtu
|
- | |
| 06 | 2.1321: Replace fossil fuel equipment with electrical equipment | $4,100 | $240 | - |
$4,100
-
MMBtu
|
- | |
| 07 | 3.1191: Change procedures / equipment / operating conditions | $14,300 | - | - | - |
$14,300
-
lb
|
|
| TOTAL RECOMMENDED | $39,940 | $97,650 |
$8,420
351,700
kWh
|
$17,220
-
MMBtu
|
$14,300
-
lb
|
||
| TOTAL IMPLEMENTED | $8,420 | $84,070 |
$8,420
351,700
kWh
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs