ITAC Assessment: GT0557
ITAC logo
ITAC Assessment: GT0557
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Lead-Acid Batteries
NAICS
n/a
SIC 3692: Primary Batteries, Dry and Wet
Sales Range $10
M
to 50
M
# of Employees 118
Plant Area 108,000
ft2
Annual Production 743,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $364,846 8,739,156
kWh
Natural Gas $106,416 18,218
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $39,940 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,420

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Solid Waste (haz) Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,590 $23,400 $2,590
107,855
kWh
- -
02 2.7144: Install spectral reflectors / delamp $910 - $910
37,808
kWh
- -
03 2.4133: Use most efficient type of electric motors $2,320 $58,400 $2,320
96,717
kWh
- -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,600 $2,270 $2,600
109,320
kWh
- -
05 2.2414: Use waste heat from hot flue gases to preheat $13,120 $13,340 - $13,120
-
MMBtu
-
06 2.1321: Replace fossil fuel equipment with electrical equipment $4,100 $240 - $4,100
-
MMBtu
-
07 3.1191: Change procedures / equipment / operating conditions $14,300 - - - $14,300
-
lb
TOTAL RECOMMENDED $39,940 $97,650 $8,420
351,700
kWh
$17,220
-
MMBtu
$14,300
-
lb
TOTAL IMPLEMENTED $8,420 $84,070 $8,420
351,700
kWh
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Solid Waste (haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs