ITAC Assessment: GT0555
ITAC logo
ITAC Assessment: GT0555
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Wood Molding
NAICS
n/a
SIC 2499: Wood Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 45
Plant Area 40,000
ft2
Annual Production 1,000
thousand feet
Production Hrs. Annual 2,375
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $68,682 595,252
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,710 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,530

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.8114: Change rate schedules or other changes in utility service $9,300 - $9,300
-
kWh
02 2.8112: Combine utility meters $980 $1,800 $980
-
kWh
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,850 $7,000 $2,850
24,912
kWh
04 2.7142: Utilize higher efficiency lamps and/or ballasts $680 $1,300 $680
5,862
kWh
05 2.6231: Utilize controls to operate equipment only when needed $3,570 $3,000 $3,570
31,067
kWh
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,330 $8,640 $2,330
20,223
kWh
TOTAL RECOMMENDED $19,710 $21,740 $19,710
82,064
kWh
TOTAL IMPLEMENTED $14,530 $6,100 $14,530
36,929
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs