ITAC Assessment: GT0540
ITAC logo
ITAC Assessment: GT0540
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Garment Elastic
NAICS
n/a
SIC 2241: Narrow Fabric and Other Smallware Mills: Cotton, Wool, Silk, and Manmade Fiber
Sales Range $10
M
to 50
M
# of Employees 199
Plant Area 50,000
ft2
Annual Production 750,000
thousand feet
Production Hrs. Annual 5,880
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $294,815 3,967,468
kWh
Natural Gas $101,997 17,442
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $75,940 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $26,010 $46,130 n/a $26,010
350,234
kWh
-
02 2.4133: Use most efficient type of electric motors $2,830 $13,160 n/a $2,830
38,101
kWh
-
03 2.2414: Use waste heat from hot flue gases to preheat $5,000 $6,500 n/a - $5,000
-
MMBtu
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $860 $960 n/a $860
11,430
kWh
-
05 2.2135: Repair and eliminate steam leaks $580 $100 n/a - $580
-
MMBtu
06 2.2511: Insulate bare equipment $3,260 $17,480 n/a - $3,260
-
MMBtu
07 2.1311: Replace electrically-operated equipment with fossil fuel equipment $37,400 $16,976 n/a $56,970
612,544
kWh
$(-19,570.0)
-
MMBtu
TOTAL RECOMMENDED $75,940 $101,306 $86,670
1,012,309
kWh
$(-10,730.0)
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs