ITAC Assessment: GT0500
ITAC logo
ITAC Assessment: GT0500
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Air Bag Inflators
NAICS
n/a
SIC 3629: Electrical Industrial Apparatus, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 115,000
ft2
Annual Production 375,000
pieces
Production Hrs. Annual 2,500
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $276,958 4,963,072
kWh
Natural Gas $16,474 2,534
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $30,370 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,870

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7135: Install occupancy sensors $170 $480 $170
2,931
kWh
02 2.2522: Isolate hot or cold equipment $1,860 $4,000 $1,860
33,411
kWh
03 2.3132: Recharge batteries on during off-peak demand periods $1,610 $500 $1,610
19,343
kWh
04 2.7229: Air condition only space necessary $24,500 $31,800 $24,500
647,714
kWh
05 2.7111: Reduce illumination to minimum necessary levels $2,230 - $2,230
39,859
kWh
TOTAL RECOMMENDED $30,370 $36,780 $30,370
743,258
kWh
TOTAL IMPLEMENTED $5,870 $4,980 $5,870
95,544
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs